Memphis Build Schedule
Habitat for Humanity
March 14 – May 10, 2008
| Date | Time | # of Vol. | Task |
Friday, March 14 |
7:30 a.m. to Noon |
30 |
Framing, Roofing, Doors, Windows, Initial Blocking, Furnace Floor |
| Noon to 5 p.m. | 30 | ||
| Saturday, March 15 | 7:30 a.m. to Noon | 30 | |
| Noon to 5 p.m. | 30 | ||
Saturday, March 29 |
7:30 a.m. to Noon | 30 |
Complete roofing and framing, begin siding |
| Noon to 5 p.m. | 30 | ||
Saturday, April 5 |
7:30 a.m. to Noon |
30 |
Complete siding, begin exterior painting, prime and paint interior trim |
| Noon to 5 p.m. | 30 | ||
Saturday, April 12 |
7:30 a.m. to Noon |
30 |
Exterior/interior painting install interior trim, and install cabinets |
| Noon-5 p.m. | 30 | ||
Saturday, April 19 |
7:30 a.m. to Noon |
30 |
Complete all interior paint and trim, install Hardware |
| Noon to 5 p.m. | 30 | ||
Saturday, April 26 |
7:30 a.m. to Noon |
30 |
Punch list and clean house |
| Noon to 5 p.m. | 30 | ||
Saturday, May 3 |
7:30 a.m. to 2 p.m.
|
30
|
Landscaping, final touches |
| Saturday, May 10 | 2 p.m. | All interested | Dedication |