tva logoTennessee Valley Authority

Industrial Custom and Prescriptive Efficiency Assistance

Project Description

TVA will fund energy evaluations and specialized consulting for industrial end-users approved requests and provide incentives for associated energy efficiency improvements. TVA will utilize in-house expertise and third party expert consultants to deliver evaluations and provide consulting services.

Incentives will be of two types:

  1. Custom incentives of $0.10 per kilowatt-hour based on the estimated first-year annual kilowatt-hour reduction resulting from the improvements.
  2. Fixed incentive amounts per installation based upon a calculated energy savings estimate for each installed measure.

Data on participants’ facilities will be captured in a central database, applying kilowatt-demand and kilowatt-hour reductions to each measure.

This project is part of the existing EnergyRight Solutions program. Budget authorization will be for at least the minimum amount to satisfy the EPA required spending commitment over the next five years.

Project Implementation

This project is comprised of three TVA efficiency offerings delivered in partnership with distributors of TVA power:

  1. Tailored solutions: (a) encourage electric energy efficiency improvements in very large industrial projects (b) customize delivery of site-specific technical assistance and incentives (c) develop and implement whole facility, multi-year energy efficiency project plans.
  2. Custom Incentives: (a) provide technical assistance to help identify custom facility and process electric savings opportunities at industrial facilities (b) custom incentive based upon first year of kilowatt-hour savings.
  3. Standard Rebates: provide prescriptive incentives for industrial customers for replacing less-efficient equipment with energy-saving technology; these measures may include lighting, HVAC, motors, office equipment, refrigeration equipment, and some process equipment.
Project Milestones Dates*
EnergyRight Solutions for Industry FY 2012 operations begin October 2011
Industrial Custom and Prescriptive Efficiency Project commissioned as part of EnergyRight Solutions for Business October 2011
Project completed Within five years of Plan approval
Report to EPA Semi-annually

* Dates are tentative and subject to change

EPA Agreement Five-Year Budget

$45 to $50 million

Contact Information

industrialefficiency@tva.com

 

Sign up to get e-mail updates on progress on these projects.

           
Content for id "future1" Goes Here
Content for id "future2" Goes Here
Content for id "future3" Goes Here