Kingston Ash Release
Weekly Progress Highlights
Each week, a status report is compiled to document the progress of the Kingston recovery effort. Highlights of those reports are presented below along with a link to the week's complete report in a PDF format. For faster viewing, a specific week can be chosen below:
Week Ending March 14, 2010
- Cumulatively, just over 2,807,400 cubic yards of ash have been removed from the river and east of Dike 2.
- To date, 176 unit trains, with a total of approximately 1,634,700 tons, have been loaded and transported to Alabama.
- No incidents occurred this week.
- Queen City Railroad completed installation of Track 3 and Norfolk Southern accepted it on March 11, 2010.
- At the request of the EPA, the Bureau of Reclamation has provided an individual to be onsite to review construction
activities on the dike. - TVA’s Ash Recovery Project General Manager presented EE/CA information to Kingston Lions Club, Harriman
Rotary, and Bearden Rotary. - Conducted March 9th Availability Session at Kingston Outreach Center from 5:30-7 p.m.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 39,625 |
2,807,410 |
| Air Testing Lab Results | 184,234 |
|
| Surface/Utility Water Lab Results | 135,895 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending March 7, 2010
- Cumulatively, just over 2,736,960 cubic yards of ash have been removed from the river and east of Dike 2.
- To date, 171 unit trains, with a total of approximately, 1,605,730 tons, have been loaded and transported to Alabama.
- A site wide safety stand down was conducted on Thursday, March 4th and Friday, March 5th. Contractor personnel reviewed work site conditions, Safe Plans of Action, and SORs.
- Lime stabilization of the ash in the east embayment began with the ash being taken to the west storage area. Rock from the upper portion of the embayment was removed and taken to a construction activity in the dredge cell.
- A contract was awarded to remove the failed skimmer wall debris. A coordination meeting between with the contractor was held.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 28,424 |
2,736,960 |
| Air Testing Lab Results | 182,441 |
|
| Surface/Utility Water Lab Results | 129,467 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending February 28, 2010
- Cumulatively, just over 2,691,736 cubic yards of ash have been removed from the river and east of Dike 2.
- To date, 166 unit trains, with a total of approximately 1,535,750 tons, have been loaded and transported to Alabama.
- The TVA General Manager of the Project presented EE/CA information to Harriman Kiwanis Club and the EPA
representative presented to Harriman Lions Club.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 46,974 |
2,691,736 |
| Air Testing Lab Results | 173,446 |
|
| Surface/Utility Water Lab Results | 129,761 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending February 21, 2010
- Cumulatively, just over 2,656,000 cubic yards of ash have been removed from the river and east of Dike 2.
- To date, 160 unit trains, with a total of approximately 1,477,760 tons, have been loaded and transported to Alabama.
- The draft of the Sampling and Analysis Plan for the River system was sent to EPA/TDEC on Monday, February 15th.
- TVA General Manager of the project reported on the progress of the ash recovery project at the end of one year to the Tennessee joint legislative committee.
- TVA General Manager of the project presented EE/CA information to two Roane County Senior Citizen groups.
- Attended and presented site updates to the Roane County Long Term Recovery Committee (LTRC).
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 34,392 |
2,656,150 |
| Air Testing Lab Results | 173,912 |
|
| Surface/Utility Water Lab Results | 129,710 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending February 14, 2010
- Cumulatively, just over 2,616,150 cubic yards of ash have been removed from the river and east of Dike 2.
- To date, 154 trains have been loaded and transported approximately 1,423,550 tons of ash.
- The northern river closed signs and booms were moved north of Emory River Mile Marker 4.5 in anticipation of dredging in this section of the river.
- Prepared and mailed letter to residents living on Emory River to publicize the extension of the Emory River closure until May 15th.
- Prepared EE/CA Fact Sheet for mailing to Roane County residents with information on how to comment on the different alternatives.
- Guest speaker presented EE/CA information to two Roane State Community College classes, Kingston Optimist Club, and the Roane Alliance Joint Industrial Economic and community Development Board.
- Met with Rockwood Mayor about approved Foundation funds for Rockwood.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 33,692 |
2,616,158 |
| Air Testing Lab Results | 173,882 |
|
| Surface/Utility Water Lab Results | 126,292 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending February 7, 2010
- Cumulatively, just over 2,570,100 cubic yards of ash have been removed from the river and east of Dike 2.
- To date149 trains have been loaded and transported approximately 1,381,900 tons of ash.
- The draft Sampling and Analysis Plan (SAP) is being reviewed.
- Made final revisions on Community Involvement Plan Responsiveness Summary and sent to EPA; began revising CIP based on comments.
- Along with EPA and TDEC, met with the Roane County Community Advisory Group.
- Met with Rockwood officials regarding recently approved Roane County Economic Development Foundation
projects.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 28,148 |
2,570,145 |
| Air Testing Lab Results | 168,976 |
|
| Surface/Utility Water Lab Results | 124,445 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending January 31, 2010
- Cumulatively, just over 2,530,900 cubic yards of ash have been removed from the river and east of Dike 2.
- To date, 147 trains have been loaded and 146 have transported approximately 1,355,240 tons of ash.
- Along with EPA and TDEC, met with the Roane County Community Advisory Group about air sampling data.
- Held public meeting at Roane County High School.
- Participated in Roane County High School teleconference with four high school classes from across the state.
- Delivered information to CAG and Swan Pond Road residents regarding the KIF Plant unit being put into operation.
- Briefed TVA Senior Management on accelerated dredge plan to achieve completion of time-critical activities by May
1, 2010.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 70,688 |
2,530,914 |
| Air Testing Lab Results | 167,986 |
|
| Surface/Utility Water Lab Results | 127,629 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending January 24, 2010
- Cumulatively, just over 2,448,300 cubic yards of ash have been removed from the river and east of Dike 2.
- To date, 144 unit trains have been loaded and transported for a total of approximately 1,331,100 tons.
- Approval to reach a height of 30 feet in the ballfield was received from EPA.
- The EE/CA for the Embayment/Dredge Cell was posted for public review on Tuesday, January 19th. Requests for
extension of the 30-day public comment period were received, and TVA and EPA agreed to extend the public
comment period another 30 days (until March 20th, 2010). - The Responsiveness Summary for the EE/CA Work Plan was finalized and posted to the TVA website on Friday,
January 22nd, 2010. - TVA, EPA, and TDEC met with the Roane County CAG at its rescheduled monthly meeting.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 69,073 |
2,448,305 |
| Air Testing Lab Results | 162,954 |
|
| Surface/Utility Water Lab Results | 118,586 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending January 17, 2010
- Cumulatively, just over 2,392,300 cubic yards of ash have been removed from the river and east of Dike 2.
- To date, 139 unit trains have been loaded and transported for a total of approximately 1,285,600 tons.
- An EPA Region 4 audit of TVA field sampling activities was conducted
- Embayment/Dredge Cell EE/CA was delivered to TVA, EPA and TDEC on Friday, January 15th, and put out for public review.
- Notified CAG and public officials of January 26, 2010 public meeting and the release of the EE/CA and placed ads in the Roane County News & Shopper for both.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 78,271 |
2,392,333 |
| Air Testing Lab Results | 160,512 |
|
| Surface/Utility Water Lab Results | 114,590 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending January 10, 2010
- Cumulatively, just over 2,323,600 cubic yards of ash have been removed from the river and east of Dike 2.
- To date, 134 unit trains have been loaded and 133 transported for a total of approximately 1,240,500 tons.
- Mayse Construction, the offsite utilities contractor, started mobilization activities for restoration of the utility lines.
- Notified public officials, Roane County CAG, and Swan Pond Road residents of third unit being turned on and of iron oxide residue discharge from south stack at KIF.
- EPA Region 4 will perform a field and data audit at the KIF site the week of January 11th. TVA sampling activities
will be observed and data packages will be reviewed.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 75,706 |
2,323,659 |
| Air Testing Lab Results | 157,480 |
|
| Surface/Utility Water Lab Results | 118,504 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending December 28, 2009
- Cumulatively, just over 2,247,923 cubic yards of ash have been removed from the river and east of Dike 2.
- We have loaded and transported 128 unit trains to date for a total of 1,192,500 tons.
- Start up of units 6 and 9 occurred at the Kingston Fossil Plant this past weekend.
- No recordable injuries or incidents reported for the week.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 31,638 |
2,247,923 |
| Air Testing Lab Results | 157,612 |
|
| Surface/Utility Water Lab Results | 117,331 |
NOTE: Total dredged from the river has been adjusted to include ongoing survey adjustments and all of TransAsh and TVA
reported hydraulic and mechanical dredging to date.
View Complete Report (PDF)
Week Ending December 20, 2009
- Cumulatively, just over 2,179,000 cubic yards of ash have been removed from the river and east of Dike 2.
- We have loaded and transported 122 unit trains to date for a total of 1,125,600 tons.
- There were no recordable incidents for the week.
- Placed a river water automated sampler in the Emory River to help with sampling during high flow events.
- TVA reported out at the Roane County Long Term Recovery Committee meeting on December 16th.
- Report to Our Roane County Neighbors, December 2009 was distributed.
- Conducted site tours and interviews with local/state media outlets showing Site progress after one year.
- The updated site-wide Kingston Emergency Action Plan was issued.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 58,620 |
2,179,079 |
| Air Testing Lab Results | 147,995 |
|
| Surface/Utility Water Lab Results | 109,754 |
Note: the Surface Water results numbers are less than last week due to an error in counting a group of samples twice last week.
View Complete Report (PDF)
Week Ending December 13, 2009
- Cumulatively, just over 2,126,500 cubic yards of ash have been removed from the river and east of Dike 2.
- Have loaded and transported 115 unit trains to date for a total of 1,051,700 tons.
- Heavy rains in the valley areas created high conditions and increased flows in the river system. Debris and
cenospheres have been identified in several areas with the majority of debris located on the far bank of the Emory
River. - Dike C buttress work began on Monday.
- EPA approved the work plans for the Filter Press and Genesis Installation; Piezometer Installation in Dredge Cell
Relic Area; Lateral Expansion Construction and Operation; and Rail Yard Modification Construction. - Availability Session was held on Tuesday, December 8th.
- The trackhoe was successfully and safely removed from the Emory River on Thursday, December 10th.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 54,440 |
2,126,568 |
| Air Testing Lab Results | 143,865 |
|
| Surface/Utility Water Lab Results | 116,889 |
View Complete Report (PDF)
Week Ending December 6, 2009
- Cumulatively, almost 2,093,000 cubic yards of ash have been removed from the river and east of Dike 2.
- Have loaded and transported 110 unit trains to date for a total of just over 1,003,000 tons – a project milestone.
- No recordable injuries or incidents reported for the week.
- EPA approved the Work Plan for Dike C reinforcement.
- Met with the CAG on Thursday night to update them on Site activities.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 84,657 |
2,092,958 |
| Air Testing Lab Results* | 142,167 |
|
| Surface/Utility Water Lab Results* | 110,496 |
*Effective with this report, air and water results will be indicated by number of lab results reported.
View Complete Report (PDF)
Week Ending November 29, 2009
- Cumulatively, just over 2,007,300 cubic yards of ash have been removed from the river and east of Dike 2.
- Have loaded and transported 106 unit trains to date for a total of approximately 961,000 tons.
- As of Wednesday afternoon, lake levels dropped to 737.38 feet MSL. Crews began looking for ash along the
exposed river banks – no large amount amounts of ash have been identified. - Delivery of sand and rock for the dike reinforcement will begin the week of November 30th.
- Informed local residents of Kingston Fossil Plant boiler maintenance issues.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 15,387 |
2,007,377 |
| Air Samples Taken | 140,987 |
|
| Surface/Utility Water Samples Taken | 20,290 |
View Complete Report (PDF)
Week Ending November 22, 2009
- Cumulatively, just over 1,989,800 cubic yards of ash have been removed from the river and east of Dike 2.
- Have loaded and transported 103 unit trains to date for a total of approximately 930,500 tons.
- Dike buttress work is scheduled to begin November 30th.
- The EE/CA for the dredge cell and embayment were submitted to EPA and TDEC for review.
- Placed Alert Today, Alive Tomorrow safety banners around site.
- Steve McCracken was introduced to Harriman City Council.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 67,296 |
1,989,855 |
| Air Samples Taken | 137,949 |
|
| Surface/Utility Water Samples Taken | 20,442 |
View Complete Report (PDF)
Week Ending November 15, 2009
- Cumulatively, just over 1,922,559 cubic yards of ash have been removed from the river and east of Dike 2.
- Have loaded and transported 97 unit trains to date for a total of approximately 866,050 tons.
- Approval to begin the final phase of the east embayment cleanup was received.
- Held Availability Session with EPA and TDEC for Roane County community.
- Met with the Community Advisory Group to negotiate the Technical Assistance Plan and agreement.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 80,127 |
1,940,559 |
| Air Samples Taken | 133,273 |
|
| Surface/Utility Water Samples Taken | 19,356 |
View Complete Report (PDF)
Week Ending November 8, 2009
- No OSHA reportable injuries this week.
- Cumulatively, just over 1,844,000 cubic yards of ash have been removed from the river and east of Dike 2.
- Submitted the Draft of Revision 4 of the Site Wide Safety and Health Plan to EPA for review.
- Have loaded and transported 91 unit trains to date for a total of approximately 809,450 tons.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 95,621 |
1,844,044 |
| Air Samples Taken | 129,840 |
|
| Surface/Utility Water Samples Taken | 17,969 |
View Complete Report (PDF)
Week Ending November 1, 2009
- An EPA safety audit was completed last week and overall feedback from the audit team was positive.
- Cumulatively, just over 1,748,400 cubic yards of ash have been removed from the river and east of Dike 2.
- Eighty-five (85) unit trains have left the site; approximately 754,100 tons of ash has been disposed of offsite.
- Contract bids for the offsite utility repair contract are due November 6, 2009 with an award projected before December 3rd.
- Submitted the revised Technical Assistance Plan.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 134,656 |
1,748,423 |
| Air Samples Taken | 124,243 |
|
| Surface/Utility Water Samples Taken | 17,891 |
View Complete Report (PDF)
Week Ending October 25, 2009
- There were no injuries or reportable releases this week.
- Cumulatively 1,617,575 cubic yards of ash have been removed from the river.
- Eighty-one unit trains have left the site; approximately 717,600 tons of ash has been disposed of offsite. Crews
began using polymer on train cars of ash to absorb water generated during transport. - A new 20” dredge was put into service replacing the existing one.
- A pre-bid meeting for the offsite utility repair contract was held on October 23rd.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 100,280 |
1,617,817 |
| Air Samples Taken | 121,643 |
|
| Surface/Utility Water Samples Taken | 17,015 |
View Complete Report (PDF)
Week Ending October 18, 2009
- One first aid incident occurred when a laborer scraped his arm while working on the new trailer complex.
- A Reportable Environmental Event (REE) occurred at the south dock when an estimated one quart of petroleum was released from the TVA 14” dredge during its transfer from the river to the ash pond.
- Total removal of time-critical ash from east of Dike 2 is approximately 1,505,000 cy.
- Total ash shipped to off-site disposal remained at 687,766 tons.
- Continuous rain throughout the week significantly impacted all recovery operations.
- River dredging operations resumed on Monday following suspension of operations on October 8th due to Free Water
Volume concerns in the ash pond.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 68,607 |
1,504,833 |
| Air Samples Taken (Through October 4) | 116,925 |
|
| Surface/Utility Water Samples Taken | 16,405 |
View Complete Report (PDF)
Week Ending October 11, 2009
- There were no safety incidents for the week.
- Moved 33,000 cy of ash from east of Dike 2.
- Issued the RFP for the offsite utility restoration effort.
- Increased the effort in cleaning out the rim ditch/sluice trench/ash pond. Are evaluating options for removing fines from the system that are hard to handle.
- Removed about 51,000 cy of ash by dredging through October 7th.
- Suspended river dredging at 11:15 on October 8th due to ash deposition in the settling pond and the corresponding reduction in Free Water Volume in the pond. The NPDES permit has a requirement to maintain a water volume of 102 million in total in both the settling pond and the stilling pond.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 84,307 |
1,436,219 |
| Air Samples Taken | 116,925 |
|
| Surface/Utility Water Samples Taken | 16,421 |
View Complete Report (PDF)
Week Ending October 4, 2009
- Moved just over 42,000 cy of ash east of Dike 2 to storage or rail cars.
- Dredged over 73,000 cy of ash from the river through October 2nd.
- Loaded and transported over 41,000 tons of ash.
- A data quality objectives workshop was held October 1st with the regulatory agencies to scope out future investigations in the river.
- A public meeting was held October 1st to inform the public of activities to date.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 115,403 |
1,405,811 |
| Air Samples Taken | 112,056 |
|
| Surface/Utility Water Samples Taken | 16,228 |
View Complete Report (PDF)
Week Ending September 27, 2009
- Moved 23,900 cy of ash east of Dike 2 to wet staging areas.
- Dredged 53,682 cy of ash from the River from September 21 to September 27.
- Moved 11,690 tons of ash this week to Alabama.
- The community Action Group (CAG) met with EPA and TVA this week.
| Key Statistics | This Week | Cumulative |
| Total Ash Removed (Cubic Yards) | 77,582 |
1,301,447 |
| Air Samples Taken | 3.138 |
110,456 |
| Water Samples Taken | 100 |
2,757 |
Note: Effective with this report, the ash information above includes all ash removed. Please see the complete report for more information.
View Complete Report (PDF)
Week Ending September 20, 2009
- Considerable rain fell beginning September 15th and continued through the week. Flood stage was not
reached in the Emory. - Moved approximately 40,000 cy of ash from September 14-20 east of Dike 2.
- Dredged 62,214 cy of ash from September 7-13 from the Emory River.
- Moved 4 unit trains offsite for approximately 39,560 tons of ash.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 62,214 |
624,231 |
| Air Samples Taken | 4,232 |
107,318 |
| Water Samples Taken | 72 |
2,657 |
View Complete Report (PDF)
Week Ending September 13, 2009
- Moved over 35,000 cy of ash from east of Dike 2 to west of Dike 2.
- Received approval to stage/process wet ash west of Dike 2.
- Current dredge positioning is requiring the bathymetric survey to be performed 3 to 5 days after excavation. This week’s dredged volumes will be reported next week. This will develop a one week lag to allow only surveyed numbers to be reported.
- Contingency plans have been put in place to support dredging.
- Transported 7 trains and 70,800 tons of ash offsite.
- Routine sampling results continue to meet all expectations.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | Next Week |
604,000 |
| Air Samples Taken | 3,007 |
105,713 |
| Water Samples Taken | 50 |
2,534 |
View Complete Report (PDF)
Week Ending September 6, 2009
- Excavated just under 40,000 cy of ash east of Dike 2 to storage areas west of Dike 2.
- Loaded and moved 7 unit trains this week for a total of 54 trains to date. Sent two 110-car trains.
- Bureau of Reclamation, TVA, TDEC, and contractors met to discuss buttressing Dike C. Agreements were reached on elements of the design.
- Transitioning to new air sampling contractor continues.
- Dredged approximately 43,900 cy from the river.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 43,940 |
604,000 |
| Air Samples Taken | 3,011 |
102,706 |
| Water Samples Taken | 50 |
2,534 |
View Complete Report (PDF)511800+
Week Ending August 30, 2009
- About 34,200 cy of ash were removed east of Dike 2.
- Improvements to dredging production were significant later in the week.
- Transported over 60,000 tons of ash offsite.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 49,330 |
560,130 |
| Air Samples Taken | 3,110 |
99,695 |
| Water Samples Taken | 49 |
2,484 |
View Complete Report (PDF)
Week Ending August 23, 2009
- Construction was completed on the clean water ditch system in Swan Pond Embayment west of Swan Pond Circle Road. Now all water either bypasses the ash or is treated in the settling basins.
- Moved approximately 24,200 cy of ash east of Dike 2 to storage areas west of Dike 2.
- Dredged over 28,000 cy for August 17-20 from the river.
- Loaded and transported over 53,000 tons of ash (6 trains) from the site.
- No safety incidents to report this week.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 28,266 |
511,800 |
| Air Samples Taken | 3,342 |
96,585 |
| Water Samples Taken | 76 |
2,435 |
View Complete Report (PDF)
Week Ending August 16, 2009
- Moved approximately 20,000 cy of ash from east of dike 2 to site storage areas.
- Began 24-hr dredging operation again. Contractor evaluating ways to improve production. Approximately 10,000 cubic yards removed.
- Completed demobilization of TransAsh.
- Loaded and transported 6 unit trains (about 53,000 tons).
- Shaw Environmental has been released to take over air monitoring.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 10,435 |
483,581 |
| Air Samples Taken | 5,512 |
93,243 |
| Water Samples Taken | 78 |
2,359 |
View Complete Report (PDF)
Week Ending August 9, 2009
- Moved approximately 21,000 cy of ash from east of Dike 2.
- Completed installation of the 1,800 feet of sheet piling along the rim ditch and of the sheet pile weirs.
- Restarted river dredging. Volumes will be estimated based on bathymetric survey information from now on and will be reported behind the weekly schedule.
- Completed baseline bathymetric survey.
- Loaded and moved 7 unit trains (roughly 63,000 tons of ash).
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 0 |
473,146 |
| Air Samples Taken | 4,620 |
87,731 |
| Water Samples Taken | 84 |
2,281 |
View Complete Report (PDF)
Week Ending August 2, 2009
- The clean water ditch in the east embayment was completed.
- Moved 13,000 cubic yards of ash from east of Dike 2 to the ash loading area.
- Began installation of sheet piling along rim ditch to stabilize the shore as well as weirs in the ditch to control hydraulics.
- Continued major dredging mobilization activity.
Transported approximately 43,000 cubic yards of ash offsite.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 0 |
473,146 |
| Air Samples Taken | 3,962 |
83,111 |
| Water Samples Taken | 68 |
2,197 |
View Complete Report (PDF)
Week Ending July 26, 2009
- Moved just under 15,000 cubic yards of ash from east of Dike 2 to disposal or storage areas.
- Suspended dredging activities to begin Rim Ditch Stabilization activities. Removed about 3,000 cubic
yards of ash prior to suspension. - First of two new large river dredges was placed in the water while the second arrived by water.
- Loaded and moved five 85-car trains this week. Landfill unloaded 44,200 tons of ash.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 3,018 |
473,146 |
| Air Samples Taken | 2,974 |
79,148 |
| Water Samples Taken | 69 |
2,129 |
View Complete Report (PDF)
View Associated Pictures (PDF)
Week Ending July 19, 2009
- Began moving ash out of the East Embayment to the new storage area West of Dike 2.
- Developed the design necessary to stabilize the rim ditch.
- Removed approximately 52,300cubic yards of ash from the River.
- Moved five 85-car trains to Alabama.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 52,276 |
470,128 |
| Air Samples Taken | 4,827 |
76,174 |
| Water Samples Taken | 98 |
2,060 |
View Complete Report (PDF)
Week Ending July 12, 2009
- Removed over 60,000 cubic yards of ash from the river via dredging.
- Removed over 22,000 cubic yards east of Dike 2.
- Began preparing a new approved temporary storage area west of Dike 2.
- Shipped approximately 34,000 tons of ash via rail offsite.
- TSS levels in the discharge from the embayment have dropped from 600-9000 mg/L to around 10 mg/L since the settling basins were put in operation last week.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 60,353 |
417,852 |
| Air Samples Taken | 5,718 |
71,347 |
| Water Samples Taken | 76 |
1,962 |
View Complete Report (PDF)
Week Ending July 5, 2009
- Moved roughly 26,000 cubic yards of ash east of Dike 2 to the ash storage area.
- The clean water ditch is now open to the river.
- Gave a notice to proceed to Sevenson Environmental Services to dredge ash out of the river long-term.
- Removed nearly 38,000 cubic yards from the river by both hydraulic and mechanical dredging.
- Loaded and sent out two unit trains of ash to Alabama for disposal.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 37,694 |
357,499 |
| Air Samples Taken | 3,696 |
65,545 |
| Water Samples Taken | 74 |
1,886 |
View Complete Report (PDF)
Week Ending June 28, 2009
- Moved just under 32,000 cubic yards of ash east of Dike 2 to the ash processing area.
- Dredged 58,700 cubic yards of ash from the river. For six days of operation, generation just over 15,000 cubic yards of ash a day from both operations.
- eld a scoping workshop with regulatory agencies to define the path forward for making non-time critical removal actions decisions.
- ork zones are being delineated and support services being put in place to allow the site to be operated as a Hazwoper site next week.
- Held a public meeting on June 23rd to listen to public concerns.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 58,692 |
327,692 |
| Air Samples Taken | 3,845 |
61,933 |
| Water Samples Taken | 95 |
1,812 |
View Complete Report (PDF)
Week Ending June 21, 2009
- Significant progress has been made in constructing the clean water ditch.
- Moved 30,000 cubic yards of ash from east of Dike 2 to the ash processing area.
- Removed approximately 39,000 cubic yards of ash from the river. Between both ash removal activities, just under 10,000 cubic yards of ash a day has been removed.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 39,000 |
269,000 |
| Air Samples Taken | 4,380 |
58,092 |
| Water Samples Taken | 95 |
1,717 |
View Complete Report (PDF)
Week Ending June 14, 2009
- Moved approximately 11,000 cubic yards of dry ash east of Dike 2 onto the ash processing area.
- Dredged approximately 24,000 cubic yards of ash from the river.
- All field activities to assess the Dike C stability are complete.
- Railroad spur Track #2 is complete as is the turnout off the main rail.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 24,200 |
230,000 |
| Air Samples Taken | 3,095 |
53,712 |
| Water Samples Taken | 88 |
1,622 |
View Complete Report (PDF)
Week Ending June 7, 2009
- Working extended hours and re-evaluating the engineering design on the interim drainage system to expedite completion of this work.
- Dredged approximately 23,600 cubic yards of river ash and 2,000 cubic yards of pond ash.
- Letters of intent to award were issued to loading, transportation, and disposal contractors.
- Repair of the riprap along Dike C was completed.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 23,600 |
199,000 |
| Air Samples Taken | 2,301 |
50,617 |
| Water Samples Taken | 65 |
1,534 |
View Complete Report (PDF)
Week Ending May 31, 2009
- Recovered just under 20,000 cubic yards of ash from the river.
- TVA 14” dredge is undergoing preparation for movement to the river.
- Track #2 (rail spur) is complete up to the guard shack.
- Best and final offers received and evaluated for loading and disposal.
- Tree removal and hole repair on Dike C completed. Stability analysis results for Dike C presented with a safety factor of 1.45.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 19,500 |
176,000 |
| Air Samples Taken | 2,398 |
48,188 |
| Water Samples Taken | 62 |
1,469 |
View Complete Report (PDF)
Week Ending May 24, 2009
- The ash stilling pond dredging was initiated and approximately 3,000 cubic yards removed.
- Held a briefing on the root cause analysis for the TDEC technical team on May 21st in Nashville.
- About 18,000 cubic yards of river ash was removed from the Emory River.
- Received EPA approval on 5 minor work plans; rail spur, rail car offloading, barge area offload, ash movement east of Dike 2, and movement of yellow dredge.
- Submitted draft safety and health plan and time critical removal action memorandum to EPA.
- Work progressing on schedule on the rail spur construction. Nearly 800 feet of rail and ties have been positioned for installation.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 17,900 |
156,000 |
| Air Samples Taken | 2,123 |
45,918 |
| Water Samples Taken | 59 |
1,407 |
View Complete Report (PDF)
Week Ending May 17, 2009
- Completed bathymetric survey on the Emory River. Results are undergoing review and will be available the week of May 18th.
- First draft of the dredging time critical action memorandum completed.
- Queen City mobilized to site and began rail spur construction.
- All rail transportation tests completed successfully with offloading of rail cars at disposal sites this week.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 14,000 |
138,000 |
| Air Samples Taken | 1,370 |
43,795 |
| Water Samples Taken | 42 |
1,288 |
View Complete Report (PDF)
Week Ending May 10, 2009
- The wet weather slowed activities on the Storm Water Management system.
- 5-year flood on the Emory River released cenospheres that were entrained with upstream debris. Extra equipment and staff were brought on board to support downstream river cleanup.
- The high water damaged river equipment and limited river dredging quantities to 4,000 cubic yards.
- Another 12,000 cubic yards was removed from the Ash Pond.
- A land and rail transportation test was held under a variety of weather conditions. Much was learned about ash containment needs in the rail cars.
- The design of the rail spur began and is nearly complete.
- Community interviews began by interviewing elected officials this week.
| Key Statistics | This Week | Cumulative |
| Ash Dredged From River (Cubic Yards) | 4,334 |
106,000 |
| Air Samples Taken | 1,940 |
42,425 |
| Water Samples Taken | 42 |
1,288 |
View Complete Report (PDF)