Hiwassee
Dam Traffic Restricted to One Lane for Maintenance
September
18,
2003
MURPHY, N. C. – Traffic on State Route 1314 across TVA’s
Hiwassee Dam will be restricted to one lane for the next six months beginning
this week for maintenance on the dam’s spillway gates, such as
sandblasting, cleaning, and painting.
Work
on each of the four spillway gates will take approximately five to
six weeks to complete.
A
traffic-control system with a maximum three-minute wait will direct
traffic across the dam throughout the six months. The roadway is
expected to reopen with two lanes of traffic on March 15, 2004.
TVA is the nation’s largest public power producer and is completely
self-financed. TVA provides power to large industries and 158 power distributors
that serve 8.3 million consumers in seven southeastern states.
Media Contact:
Michelle
Chang, Knoxville (865-632-8108) or TVA News Bureau, Knoxville
(865-632-6000)

|