Artesia, Mississippi
Update — August 2020
TVA has completed an Environmental Assessment for the proposed 12-mile transmission line that would increase customer reliability and support economic development. The environmental documents are available here.
Update — June 2018
TVA has identified preferred locations for transmission upgrades that would increase customer reliability and support economic development at the Infinity Megasite (Megasite) near Artesia, Mississippi.
TVA proposes to build a transmission line and switching station. The new line would begin at TVA’s West Columbus Switching Station on the southeast side of U.S. Highway 45 and then head southwest for 11 miles ending at the new Artesia 161-kV Switching Station.
For four miles, the new line would parallel a portion of TVA’s West Columbus-Severcorr Transmission Line which would be torn down and rebuilt as a double circuit.
The preferred route is No. 1 which consists of segment Nos. 1, 2, 9, 13, 14, 15, 16, and 24 as presented at the open house in January 2018.
TVA evaluated each route using social, engineering, and environmental factors. Information sources included available data, aerial photography, limited onsite reviews, public review and comment, and property owner input. Based on public input and evaluation, the preferred route is expected to have the least overall project impacts of the alternatives.
The new line would consist of steel poles centered on new and existing 100-foot-wide right of way.
Surveys of the right of way are scheduled to begin in winter 2018.
Easement purchases are scheduled to begin in winter 2019.
Construction is scheduled to begin in spring 2021.
The line is scheduled to be in service in fall 2021.
Background
TVA is proposing to build 11 to 13 miles of 161-kV transmission line and a switching station.
The new line would provide power to a switching station TVA proposes to build at the Megasite near the Golden Triangle Regional Airport south of U.S. Highway 82 between Starkville and Columbus.
There are about 24 alternative transmission line routes consisting of 24 alternative line segments under consideration. The line would be built on steel pole structures.
Existing transmission line resources would be utilized where possible. The alternative routes would also involve tearing down and rebuilding portions of the West Columbus Switching Station-Severcorr Switching Station Transmission Line. These portions range from 3 to 4.5 miles long and would be rebuilt as double-circuit on the existing right of way. In some instances, the rebuild would require expanding the right of way from 75 to 100 feet wide.
TVA will hold an open house on January 18, 2018, to provide information, answer questions and receive comments about the proposed transmission project.
The project is expected to be in service in fall 2021. Construction is scheduled to begin in summer 2021. (Dates are subject to change. During projects of this magnitude, unexpected issues may arise, resulting in the need to adjust the schedule.)
Public Involvement
Map
The map shows the area of the proposed transmission improvements. The map is also available below as a PDF file.
If you have questions or need help understanding the map, please contact TVA (see below).
Preferred route of proposed transmission line (PDF)
Possible routes of proposed transmission line (PDF, 7.9 mb)
Project Schedule
(Dates are subject to change. During projects of this magnitude, unexpected issues may arise, resulting in the need to adjust the schedule.)
Open house | Jan 18, 2018 |
Comments accepted | Feb 20, 2018 |
Determine preferred route for field surveys | late spring 2018 |
Surveys of the right of way are scheduled to begin | winter 2018 |
Easement purchases are scheduled to begin | winter 2019 |
Construction is scheduled to begin | spring 2021 |
Project in service | fall 2021 |
Environmental Reviews
The appropriate National Environmental Policy Act review will be conducted to ensure that the environmental impacts are minimized. TVA attempts to minimize any land requirements, private property impacts, and environmental impacts associated with this project.
Efforts are made during the siting process to avoid or minimize impacts to floodplains and wetlands in accordance with Executive Orders 11988 and 11990. Floodplains and wetlands are shown on the referenced map. The map illustrates how the route avoids or impacts floodplains and wetlands. Because of project and topographic constraints and because of minimizing impacts to other social, environmental, and engineering resources, no practicable alternative may be available that would allow complete avoidance of impacts to floodplains and wetlands which may require mitigation for minimizing impacts. Also, best management practices would be utilized throughout the project to minimize adverse floodplain and wetland impacts. In compliance with Section 404 of the Clean Water Act, TVA will be coordinating wetland findings with U.S. Army Corps of Engineers.
Contact
More information on this project can be obtained from:
Kelly Evans
[email protected]
800-362-4355
1101 Market Street, MR 4G
Chattanooga,
TN
37402