Skip to main content

Current TVA Transmission System Projects

Alabama

Star Gap, Alabama (Fort Payne, DeKalb County)

Proposed Transmission Project

TVA is considering improvements to its transmission system that would provide power for growing load and increase power reliability in the Fort Payne area of DeKalb County in Alabama.

The Fort Payne Improvement Authority (FPIA) operates a network of seven substations at 161-kilovolt, 115-kilovolt, and 46-kilovolt across Dekalb County.  FPIA’s Fort Payne District 46-kilovolt Substation is served by a pair of their own 4.1-mile, 46-kilovolt transmission lines by a 46-kilovolt breaker at TVA’s Fort Payne 161-kilovolt Substation.

FPIA’s Fort Payne District 46-kilovolt Substation was built in 1958, and test reports on the transformers have shown increased deterioration.  FPIA has also stated that the existing 46-kilovolt transmission line is showing signs of age, and they are facing challenges maintaining the line due to its location on the side of the southern ridge of Fort Payne.  The Fort Payne District 46-kilovolt Substation represents an increasing reliability risk due to its advanced age and the lack of in-house options to address issues on the 46-kilovolt transmission line which supplies the station.

TVA and FPIA propose to address these issues by building a new 161-kilovolt delivery point which would include the construction of FPIA’s new Star Gap 161-kilovolt Substation and about 3.5 miles of new TVA 161-kilovolt transmission line originating at TVA’s Fort Payne 161-kilovolt Substation.  This effort will also include retiring FPIA’s existing Fort Payne District 46-kilovolt Substation as well as their existing pair of 4.1-mile, 46-kilovolt transmission lines.  The Alternative 46-kilovolt line will be deconstructed before TVA’s proposed 161-kilovolt transmission line is built.  FPIA’s existing Fort Payne District 46-kilovolt Substation and Primary 46-kilovolt feed line will remain in service during construction of the proposed substation and transmission line and will be deconstructed following their completion.

FPIA will build the Star Gap Substation at the corner of 8th Street NE and Wallace Avenue NE in Fort Payne.  TVA will build about 3.5 miles of single-circuit transmission line using primarily single-pole, steel structures with the potential for H-frame structures as dictated by the terrain.  TVA’s line would begin at the existing Fort Payne 161-kilovolt Substation and extend southwest to the new Star Gap Substation. 

TVA’s proposed line will utilize a combination of existing and new rights of way.  TVA will acquire additional easement as needed for the new line. 

TVA will hold an information day on May 1, 2025, to provide information and answer questions about the proposed transmission project.  For those unable to attend the information day on May 1, TVA is providing a virtual information session from May 1 through May 30, 2025, online at tvavirtual.com/stargap.

The project is expected to be in service in fall 2028.  Construction is scheduled to begin in spring-summer 2028.  (Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Single Pole Circuit Double circuit transmission line

Public Involvement

TVA is committed to working with area stakeholders to address concerns during various stages of the project.  TVA will hold an information day and virtual information session to discuss the proposed transmission project. Details are as follows:

Thursday, May 1, 2025, 3:00 - 7:00 p.m., local time
The Building,
301 Gault Avenue
North Fort Payne, Alabama 35967

TVA representatives will be available at the information day to provide information and answer questions. Large maps showing the alternative locations for consideration will be available.

Any questions received, including names and addresses, will become part of the administrative record.

If you have special needs, please contact Tanya Adams at least five days prior to the information day toll-free at (800) 362-4355.

If you cannot attend the information day but have questions, contact Kevin Casler (see contact information below).

SUBMIT QUESTIONS ABOUT THE PROJECT

Map

The map shows the area of the proposed transmission improvements. The map is also available below as a PDF file.

If you have questions or need help understanding the map, please contact TVA (see below).

Star Gap, Alabama Open House Map

Project Schedule

(Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Information DayMay 1, 2025
Virtual Information SessionMay 1 through May 30, 2025
Surveys of the right of way are scheduled to beginSummer–Fall 2025
Easement purchases are scheduled to beginFall 2026–Winter 2026-2027
Construction is scheduled to begin Spring–Summer 2028
Project in service Fall 2028

Environmental Reviews

The appropriate National Environmental Policy Act review will be conducted to ensure that the environmental impacts are minimized. TVA attempts to minimize any land requirements, private property impacts, and environmental impacts associated with this project.

Efforts are made during the siting process to avoid or minimize impacts to floodplains and wetlands in accordance with Executive Orders 11988 and 11990. Floodplains and wetlands are shown on the referenced map. The map illustrates how the route avoids or impacts floodplains and wetlands. Because of project and topographic constraints and because of minimizing impacts to other social, environmental, and engineering resources, no practicable alternative may be available that would allow complete avoidance of impacts to floodplains and wetlands which may require mitigation for minimizing impacts. Also, best management practices would be utilized throughout the project to minimize adverse floodplain and wetland impacts. In compliance with Section 404 of the Clean Water Act, TVA will be coordinating wetland findings with U.S. Army Corps of Engineers.

Contact

More information on this project can be obtained from:

Kevin Casler, P.E.
[email protected]
800-362-4355
1101 Market Street, MR 4G
Chattanooga, TN 37402-2801

Georgia

Star Gap, Alabama (Fort Payne, DeKalb County)

Proposed Transmission Project

TVA is considering improvements to its transmission system that would provide power for growing load and increase power reliability in the Fort Payne area of DeKalb County in Alabama.

The Fort Payne Improvement Authority (FPIA) operates a network of seven substations at 161-kilovolt, 115-kilovolt, and 46-kilovolt across Dekalb County.  FPIA’s Fort Payne District 46-kilovolt Substation is served by a pair of their own 4.1-mile, 46-kilovolt transmission lines by a 46-kilovolt breaker at TVA’s Fort Payne 161-kilovolt Substation.

FPIA’s Fort Payne District 46-kilovolt Substation was built in 1958, and test reports on the transformers have shown increased deterioration.  FPIA has also stated that the existing 46-kilovolt transmission line is showing signs of age, and they are facing challenges maintaining the line due to its location on the side of the southern ridge of Fort Payne.  The Fort Payne District 46-kilovolt Substation represents an increasing reliability risk due to its advanced age and the lack of in-house options to address issues on the 46-kilovolt transmission line which supplies the station.

TVA and FPIA propose to address these issues by building a new 161-kilovolt delivery point which would include the construction of FPIA’s new Star Gap 161-kilovolt Substation and about 3.5 miles of new TVA 161-kilovolt transmission line originating at TVA’s Fort Payne 161-kilovolt Substation.  This effort will also include retiring FPIA’s existing Fort Payne District 46-kilovolt Substation as well as their existing pair of 4.1-mile, 46-kilovolt transmission lines.  The Alternative 46-kilovolt line will be deconstructed before TVA’s proposed 161-kilovolt transmission line is built.  FPIA’s existing Fort Payne District 46-kilovolt Substation and Primary 46-kilovolt feed line will remain in service during construction of the proposed substation and transmission line and will be deconstructed following their completion.

FPIA will build the Star Gap Substation at the corner of 8th Street NE and Wallace Avenue NE in Fort Payne.  TVA will build about 3.5 miles of single-circuit transmission line using primarily single-pole, steel structures with the potential for H-frame structures as dictated by the terrain.  TVA’s line would begin at the existing Fort Payne 161-kilovolt Substation and extend southwest to the new Star Gap Substation. 

TVA’s proposed line will utilize a combination of existing and new rights of way.  TVA will acquire additional easement as needed for the new line. 

TVA will hold an information day on May 1, 2025, to provide information and answer questions about the proposed transmission project.  For those unable to attend the information day on May 1, TVA is providing a virtual information session from May 1 through May 30, 2025, online at tvavirtual.com/stargap.

The project is expected to be in service in fall 2028.  Construction is scheduled to begin in spring-summer 2028.  (Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Single Pole Circuit Double circuit transmission line

Public Involvement

TVA is committed to working with area stakeholders to address concerns during various stages of the project.  TVA will hold an information day and virtual information session to discuss the proposed transmission project. Details are as follows:

Thursday, May 1, 2025, 3:00 - 7:00 p.m., local time
The Building,
301 Gault Avenue
North Fort Payne, Alabama 35967

TVA representatives will be available at the information day to provide information and answer questions. Large maps showing the alternative locations for consideration will be available.

Any questions received, including names and addresses, will become part of the administrative record.

If you have special needs, please contact Tanya Adams at least five days prior to the information day toll-free at (800) 362-4355.

If you cannot attend the information day but have questions, contact Kevin Casler (see contact information below).

SUBMIT QUESTIONS ABOUT THE PROJECT

Map

The map shows the area of the proposed transmission improvements. The map is also available below as a PDF file.

If you have questions or need help understanding the map, please contact TVA (see below).

Star Gap, Alabama Open House Map

Project Schedule

(Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Information DayMay 1, 2025
Virtual Information SessionMay 1 through May 30, 2025
Surveys of the right of way are scheduled to beginSummer–Fall 2025
Easement purchases are scheduled to beginFall 2026–Winter 2026-2027
Construction is scheduled to begin Spring–Summer 2028
Project in service Fall 2028

Environmental Reviews

The appropriate National Environmental Policy Act review will be conducted to ensure that the environmental impacts are minimized. TVA attempts to minimize any land requirements, private property impacts, and environmental impacts associated with this project.

Efforts are made during the siting process to avoid or minimize impacts to floodplains and wetlands in accordance with Executive Orders 11988 and 11990. Floodplains and wetlands are shown on the referenced map. The map illustrates how the route avoids or impacts floodplains and wetlands. Because of project and topographic constraints and because of minimizing impacts to other social, environmental, and engineering resources, no practicable alternative may be available that would allow complete avoidance of impacts to floodplains and wetlands which may require mitigation for minimizing impacts. Also, best management practices would be utilized throughout the project to minimize adverse floodplain and wetland impacts. In compliance with Section 404 of the Clean Water Act, TVA will be coordinating wetland findings with U.S. Army Corps of Engineers.

Contact

More information on this project can be obtained from:

Kevin Casler, P.E.
[email protected]
800-362-4355
1101 Market Street, MR 4G
Chattanooga, TN 37402-2801

Kentucky

Star Gap, Alabama (Fort Payne, DeKalb County)

Proposed Transmission Project

TVA is considering improvements to its transmission system that would provide power for growing load and increase power reliability in the Fort Payne area of DeKalb County in Alabama.

The Fort Payne Improvement Authority (FPIA) operates a network of seven substations at 161-kilovolt, 115-kilovolt, and 46-kilovolt across Dekalb County.  FPIA’s Fort Payne District 46-kilovolt Substation is served by a pair of their own 4.1-mile, 46-kilovolt transmission lines by a 46-kilovolt breaker at TVA’s Fort Payne 161-kilovolt Substation.

FPIA’s Fort Payne District 46-kilovolt Substation was built in 1958, and test reports on the transformers have shown increased deterioration.  FPIA has also stated that the existing 46-kilovolt transmission line is showing signs of age, and they are facing challenges maintaining the line due to its location on the side of the southern ridge of Fort Payne.  The Fort Payne District 46-kilovolt Substation represents an increasing reliability risk due to its advanced age and the lack of in-house options to address issues on the 46-kilovolt transmission line which supplies the station.

TVA and FPIA propose to address these issues by building a new 161-kilovolt delivery point which would include the construction of FPIA’s new Star Gap 161-kilovolt Substation and about 3.5 miles of new TVA 161-kilovolt transmission line originating at TVA’s Fort Payne 161-kilovolt Substation.  This effort will also include retiring FPIA’s existing Fort Payne District 46-kilovolt Substation as well as their existing pair of 4.1-mile, 46-kilovolt transmission lines.  The Alternative 46-kilovolt line will be deconstructed before TVA’s proposed 161-kilovolt transmission line is built.  FPIA’s existing Fort Payne District 46-kilovolt Substation and Primary 46-kilovolt feed line will remain in service during construction of the proposed substation and transmission line and will be deconstructed following their completion.

FPIA will build the Star Gap Substation at the corner of 8th Street NE and Wallace Avenue NE in Fort Payne.  TVA will build about 3.5 miles of single-circuit transmission line using primarily single-pole, steel structures with the potential for H-frame structures as dictated by the terrain.  TVA’s line would begin at the existing Fort Payne 161-kilovolt Substation and extend southwest to the new Star Gap Substation. 

TVA’s proposed line will utilize a combination of existing and new rights of way.  TVA will acquire additional easement as needed for the new line. 

TVA will hold an information day on May 1, 2025, to provide information and answer questions about the proposed transmission project.  For those unable to attend the information day on May 1, TVA is providing a virtual information session from May 1 through May 30, 2025, online at tvavirtual.com/stargap.

The project is expected to be in service in fall 2028.  Construction is scheduled to begin in spring-summer 2028.  (Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Single Pole Circuit Double circuit transmission line

Public Involvement

TVA is committed to working with area stakeholders to address concerns during various stages of the project.  TVA will hold an information day and virtual information session to discuss the proposed transmission project. Details are as follows:

Thursday, May 1, 2025, 3:00 - 7:00 p.m., local time
The Building,
301 Gault Avenue
North Fort Payne, Alabama 35967

TVA representatives will be available at the information day to provide information and answer questions. Large maps showing the alternative locations for consideration will be available.

Any questions received, including names and addresses, will become part of the administrative record.

If you have special needs, please contact Tanya Adams at least five days prior to the information day toll-free at (800) 362-4355.

If you cannot attend the information day but have questions, contact Kevin Casler (see contact information below).

SUBMIT QUESTIONS ABOUT THE PROJECT

Map

The map shows the area of the proposed transmission improvements. The map is also available below as a PDF file.

If you have questions or need help understanding the map, please contact TVA (see below).

Star Gap, Alabama Open House Map

Project Schedule

(Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Information DayMay 1, 2025
Virtual Information SessionMay 1 through May 30, 2025
Surveys of the right of way are scheduled to beginSummer–Fall 2025
Easement purchases are scheduled to beginFall 2026–Winter 2026-2027
Construction is scheduled to begin Spring–Summer 2028
Project in service Fall 2028

Environmental Reviews

The appropriate National Environmental Policy Act review will be conducted to ensure that the environmental impacts are minimized. TVA attempts to minimize any land requirements, private property impacts, and environmental impacts associated with this project.

Efforts are made during the siting process to avoid or minimize impacts to floodplains and wetlands in accordance with Executive Orders 11988 and 11990. Floodplains and wetlands are shown on the referenced map. The map illustrates how the route avoids or impacts floodplains and wetlands. Because of project and topographic constraints and because of minimizing impacts to other social, environmental, and engineering resources, no practicable alternative may be available that would allow complete avoidance of impacts to floodplains and wetlands which may require mitigation for minimizing impacts. Also, best management practices would be utilized throughout the project to minimize adverse floodplain and wetland impacts. In compliance with Section 404 of the Clean Water Act, TVA will be coordinating wetland findings with U.S. Army Corps of Engineers.

Contact

More information on this project can be obtained from:

Kevin Casler, P.E.
[email protected]
800-362-4355
1101 Market Street, MR 4G
Chattanooga, TN 37402-2801

Mississippi

Star Gap, Alabama (Fort Payne, DeKalb County)

Proposed Transmission Project

TVA is considering improvements to its transmission system that would provide power for growing load and increase power reliability in the Fort Payne area of DeKalb County in Alabama.

The Fort Payne Improvement Authority (FPIA) operates a network of seven substations at 161-kilovolt, 115-kilovolt, and 46-kilovolt across Dekalb County.  FPIA’s Fort Payne District 46-kilovolt Substation is served by a pair of their own 4.1-mile, 46-kilovolt transmission lines by a 46-kilovolt breaker at TVA’s Fort Payne 161-kilovolt Substation.

FPIA’s Fort Payne District 46-kilovolt Substation was built in 1958, and test reports on the transformers have shown increased deterioration.  FPIA has also stated that the existing 46-kilovolt transmission line is showing signs of age, and they are facing challenges maintaining the line due to its location on the side of the southern ridge of Fort Payne.  The Fort Payne District 46-kilovolt Substation represents an increasing reliability risk due to its advanced age and the lack of in-house options to address issues on the 46-kilovolt transmission line which supplies the station.

TVA and FPIA propose to address these issues by building a new 161-kilovolt delivery point which would include the construction of FPIA’s new Star Gap 161-kilovolt Substation and about 3.5 miles of new TVA 161-kilovolt transmission line originating at TVA’s Fort Payne 161-kilovolt Substation.  This effort will also include retiring FPIA’s existing Fort Payne District 46-kilovolt Substation as well as their existing pair of 4.1-mile, 46-kilovolt transmission lines.  The Alternative 46-kilovolt line will be deconstructed before TVA’s proposed 161-kilovolt transmission line is built.  FPIA’s existing Fort Payne District 46-kilovolt Substation and Primary 46-kilovolt feed line will remain in service during construction of the proposed substation and transmission line and will be deconstructed following their completion.

FPIA will build the Star Gap Substation at the corner of 8th Street NE and Wallace Avenue NE in Fort Payne.  TVA will build about 3.5 miles of single-circuit transmission line using primarily single-pole, steel structures with the potential for H-frame structures as dictated by the terrain.  TVA’s line would begin at the existing Fort Payne 161-kilovolt Substation and extend southwest to the new Star Gap Substation. 

TVA’s proposed line will utilize a combination of existing and new rights of way.  TVA will acquire additional easement as needed for the new line. 

TVA will hold an information day on May 1, 2025, to provide information and answer questions about the proposed transmission project.  For those unable to attend the information day on May 1, TVA is providing a virtual information session from May 1 through May 30, 2025, online at tvavirtual.com/stargap.

The project is expected to be in service in fall 2028.  Construction is scheduled to begin in spring-summer 2028.  (Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Single Pole Circuit Double circuit transmission line

Public Involvement

TVA is committed to working with area stakeholders to address concerns during various stages of the project.  TVA will hold an information day and virtual information session to discuss the proposed transmission project. Details are as follows:

Thursday, May 1, 2025, 3:00 - 7:00 p.m., local time
The Building,
301 Gault Avenue
North Fort Payne, Alabama 35967

TVA representatives will be available at the information day to provide information and answer questions. Large maps showing the alternative locations for consideration will be available.

Any questions received, including names and addresses, will become part of the administrative record.

If you have special needs, please contact Tanya Adams at least five days prior to the information day toll-free at (800) 362-4355.

If you cannot attend the information day but have questions, contact Kevin Casler (see contact information below).

SUBMIT QUESTIONS ABOUT THE PROJECT

Map

The map shows the area of the proposed transmission improvements. The map is also available below as a PDF file.

If you have questions or need help understanding the map, please contact TVA (see below).

Star Gap, Alabama Open House Map

Project Schedule

(Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Information DayMay 1, 2025
Virtual Information SessionMay 1 through May 30, 2025
Surveys of the right of way are scheduled to beginSummer–Fall 2025
Easement purchases are scheduled to beginFall 2026–Winter 2026-2027
Construction is scheduled to begin Spring–Summer 2028
Project in service Fall 2028

Environmental Reviews

The appropriate National Environmental Policy Act review will be conducted to ensure that the environmental impacts are minimized. TVA attempts to minimize any land requirements, private property impacts, and environmental impacts associated with this project.

Efforts are made during the siting process to avoid or minimize impacts to floodplains and wetlands in accordance with Executive Orders 11988 and 11990. Floodplains and wetlands are shown on the referenced map. The map illustrates how the route avoids or impacts floodplains and wetlands. Because of project and topographic constraints and because of minimizing impacts to other social, environmental, and engineering resources, no practicable alternative may be available that would allow complete avoidance of impacts to floodplains and wetlands which may require mitigation for minimizing impacts. Also, best management practices would be utilized throughout the project to minimize adverse floodplain and wetland impacts. In compliance with Section 404 of the Clean Water Act, TVA will be coordinating wetland findings with U.S. Army Corps of Engineers.

Contact

More information on this project can be obtained from:

Kevin Casler, P.E.
[email protected]
800-362-4355
1101 Market Street, MR 4G
Chattanooga, TN 37402-2801

North Carolina

Star Gap, Alabama (Fort Payne, DeKalb County)

Proposed Transmission Project

TVA is considering improvements to its transmission system that would provide power for growing load and increase power reliability in the Fort Payne area of DeKalb County in Alabama.

The Fort Payne Improvement Authority (FPIA) operates a network of seven substations at 161-kilovolt, 115-kilovolt, and 46-kilovolt across Dekalb County.  FPIA’s Fort Payne District 46-kilovolt Substation is served by a pair of their own 4.1-mile, 46-kilovolt transmission lines by a 46-kilovolt breaker at TVA’s Fort Payne 161-kilovolt Substation.

FPIA’s Fort Payne District 46-kilovolt Substation was built in 1958, and test reports on the transformers have shown increased deterioration.  FPIA has also stated that the existing 46-kilovolt transmission line is showing signs of age, and they are facing challenges maintaining the line due to its location on the side of the southern ridge of Fort Payne.  The Fort Payne District 46-kilovolt Substation represents an increasing reliability risk due to its advanced age and the lack of in-house options to address issues on the 46-kilovolt transmission line which supplies the station.

TVA and FPIA propose to address these issues by building a new 161-kilovolt delivery point which would include the construction of FPIA’s new Star Gap 161-kilovolt Substation and about 3.5 miles of new TVA 161-kilovolt transmission line originating at TVA’s Fort Payne 161-kilovolt Substation.  This effort will also include retiring FPIA’s existing Fort Payne District 46-kilovolt Substation as well as their existing pair of 4.1-mile, 46-kilovolt transmission lines.  The Alternative 46-kilovolt line will be deconstructed before TVA’s proposed 161-kilovolt transmission line is built.  FPIA’s existing Fort Payne District 46-kilovolt Substation and Primary 46-kilovolt feed line will remain in service during construction of the proposed substation and transmission line and will be deconstructed following their completion.

FPIA will build the Star Gap Substation at the corner of 8th Street NE and Wallace Avenue NE in Fort Payne.  TVA will build about 3.5 miles of single-circuit transmission line using primarily single-pole, steel structures with the potential for H-frame structures as dictated by the terrain.  TVA’s line would begin at the existing Fort Payne 161-kilovolt Substation and extend southwest to the new Star Gap Substation. 

TVA’s proposed line will utilize a combination of existing and new rights of way.  TVA will acquire additional easement as needed for the new line. 

TVA will hold an information day on May 1, 2025, to provide information and answer questions about the proposed transmission project.  For those unable to attend the information day on May 1, TVA is providing a virtual information session from May 1 through May 30, 2025, online at tvavirtual.com/stargap.

The project is expected to be in service in fall 2028.  Construction is scheduled to begin in spring-summer 2028.  (Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Single Pole Circuit Double circuit transmission line

Public Involvement

TVA is committed to working with area stakeholders to address concerns during various stages of the project.  TVA will hold an information day and virtual information session to discuss the proposed transmission project. Details are as follows:

Thursday, May 1, 2025, 3:00 - 7:00 p.m., local time
The Building,
301 Gault Avenue
North Fort Payne, Alabama 35967

TVA representatives will be available at the information day to provide information and answer questions. Large maps showing the alternative locations for consideration will be available.

Any questions received, including names and addresses, will become part of the administrative record.

If you have special needs, please contact Tanya Adams at least five days prior to the information day toll-free at (800) 362-4355.

If you cannot attend the information day but have questions, contact Kevin Casler (see contact information below).

SUBMIT QUESTIONS ABOUT THE PROJECT

Map

The map shows the area of the proposed transmission improvements. The map is also available below as a PDF file.

If you have questions or need help understanding the map, please contact TVA (see below).

Star Gap, Alabama Open House Map

Project Schedule

(Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Information DayMay 1, 2025
Virtual Information SessionMay 1 through May 30, 2025
Surveys of the right of way are scheduled to beginSummer–Fall 2025
Easement purchases are scheduled to beginFall 2026–Winter 2026-2027
Construction is scheduled to begin Spring–Summer 2028
Project in service Fall 2028

Environmental Reviews

The appropriate National Environmental Policy Act review will be conducted to ensure that the environmental impacts are minimized. TVA attempts to minimize any land requirements, private property impacts, and environmental impacts associated with this project.

Efforts are made during the siting process to avoid or minimize impacts to floodplains and wetlands in accordance with Executive Orders 11988 and 11990. Floodplains and wetlands are shown on the referenced map. The map illustrates how the route avoids or impacts floodplains and wetlands. Because of project and topographic constraints and because of minimizing impacts to other social, environmental, and engineering resources, no practicable alternative may be available that would allow complete avoidance of impacts to floodplains and wetlands which may require mitigation for minimizing impacts. Also, best management practices would be utilized throughout the project to minimize adverse floodplain and wetland impacts. In compliance with Section 404 of the Clean Water Act, TVA will be coordinating wetland findings with U.S. Army Corps of Engineers.

Contact

More information on this project can be obtained from:

Kevin Casler, P.E.
[email protected]
800-362-4355
1101 Market Street, MR 4G
Chattanooga, TN 37402-2801

Tennessee

Star Gap, Alabama (Fort Payne, DeKalb County)

Proposed Transmission Project

TVA is considering improvements to its transmission system that would provide power for growing load and increase power reliability in the Fort Payne area of DeKalb County in Alabama.

The Fort Payne Improvement Authority (FPIA) operates a network of seven substations at 161-kilovolt, 115-kilovolt, and 46-kilovolt across Dekalb County.  FPIA’s Fort Payne District 46-kilovolt Substation is served by a pair of their own 4.1-mile, 46-kilovolt transmission lines by a 46-kilovolt breaker at TVA’s Fort Payne 161-kilovolt Substation.

FPIA’s Fort Payne District 46-kilovolt Substation was built in 1958, and test reports on the transformers have shown increased deterioration.  FPIA has also stated that the existing 46-kilovolt transmission line is showing signs of age, and they are facing challenges maintaining the line due to its location on the side of the southern ridge of Fort Payne.  The Fort Payne District 46-kilovolt Substation represents an increasing reliability risk due to its advanced age and the lack of in-house options to address issues on the 46-kilovolt transmission line which supplies the station.

TVA and FPIA propose to address these issues by building a new 161-kilovolt delivery point which would include the construction of FPIA’s new Star Gap 161-kilovolt Substation and about 3.5 miles of new TVA 161-kilovolt transmission line originating at TVA’s Fort Payne 161-kilovolt Substation.  This effort will also include retiring FPIA’s existing Fort Payne District 46-kilovolt Substation as well as their existing pair of 4.1-mile, 46-kilovolt transmission lines.  The Alternative 46-kilovolt line will be deconstructed before TVA’s proposed 161-kilovolt transmission line is built.  FPIA’s existing Fort Payne District 46-kilovolt Substation and Primary 46-kilovolt feed line will remain in service during construction of the proposed substation and transmission line and will be deconstructed following their completion.

FPIA will build the Star Gap Substation at the corner of 8th Street NE and Wallace Avenue NE in Fort Payne.  TVA will build about 3.5 miles of single-circuit transmission line using primarily single-pole, steel structures with the potential for H-frame structures as dictated by the terrain.  TVA’s line would begin at the existing Fort Payne 161-kilovolt Substation and extend southwest to the new Star Gap Substation. 

TVA’s proposed line will utilize a combination of existing and new rights of way.  TVA will acquire additional easement as needed for the new line. 

TVA will hold an information day on May 1, 2025, to provide information and answer questions about the proposed transmission project.  For those unable to attend the information day on May 1, TVA is providing a virtual information session from May 1 through May 30, 2025, online at tvavirtual.com/stargap.

The project is expected to be in service in fall 2028.  Construction is scheduled to begin in spring-summer 2028.  (Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Single Pole Circuit Double circuit transmission line

Public Involvement

TVA is committed to working with area stakeholders to address concerns during various stages of the project.  TVA will hold an information day and virtual information session to discuss the proposed transmission project. Details are as follows:

Thursday, May 1, 2025, 3:00 - 7:00 p.m., local time
The Building,
301 Gault Avenue
North Fort Payne, Alabama 35967

TVA representatives will be available at the information day to provide information and answer questions. Large maps showing the alternative locations for consideration will be available.

Any questions received, including names and addresses, will become part of the administrative record.

If you have special needs, please contact Tanya Adams at least five days prior to the information day toll-free at (800) 362-4355.

If you cannot attend the information day but have questions, contact Kevin Casler (see contact information below).

SUBMIT QUESTIONS ABOUT THE PROJECT

Map

The map shows the area of the proposed transmission improvements. The map is also available below as a PDF file.

If you have questions or need help understanding the map, please contact TVA (see below).

Star Gap, Alabama Open House Map

Project Schedule

(Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Information DayMay 1, 2025
Virtual Information SessionMay 1 through May 30, 2025
Surveys of the right of way are scheduled to beginSummer–Fall 2025
Easement purchases are scheduled to beginFall 2026–Winter 2026-2027
Construction is scheduled to begin Spring–Summer 2028
Project in service Fall 2028

Environmental Reviews

The appropriate National Environmental Policy Act review will be conducted to ensure that the environmental impacts are minimized. TVA attempts to minimize any land requirements, private property impacts, and environmental impacts associated with this project.

Efforts are made during the siting process to avoid or minimize impacts to floodplains and wetlands in accordance with Executive Orders 11988 and 11990. Floodplains and wetlands are shown on the referenced map. The map illustrates how the route avoids or impacts floodplains and wetlands. Because of project and topographic constraints and because of minimizing impacts to other social, environmental, and engineering resources, no practicable alternative may be available that would allow complete avoidance of impacts to floodplains and wetlands which may require mitigation for minimizing impacts. Also, best management practices would be utilized throughout the project to minimize adverse floodplain and wetland impacts. In compliance with Section 404 of the Clean Water Act, TVA will be coordinating wetland findings with U.S. Army Corps of Engineers.

Contact

More information on this project can be obtained from:

Kevin Casler, P.E.
[email protected]
800-362-4355
1101 Market Street, MR 4G
Chattanooga, TN 37402-2801

Virginia

Star Gap, Alabama (Fort Payne, DeKalb County)

Proposed Transmission Project

TVA is considering improvements to its transmission system that would provide power for growing load and increase power reliability in the Fort Payne area of DeKalb County in Alabama.

The Fort Payne Improvement Authority (FPIA) operates a network of seven substations at 161-kilovolt, 115-kilovolt, and 46-kilovolt across Dekalb County.  FPIA’s Fort Payne District 46-kilovolt Substation is served by a pair of their own 4.1-mile, 46-kilovolt transmission lines by a 46-kilovolt breaker at TVA’s Fort Payne 161-kilovolt Substation.

FPIA’s Fort Payne District 46-kilovolt Substation was built in 1958, and test reports on the transformers have shown increased deterioration.  FPIA has also stated that the existing 46-kilovolt transmission line is showing signs of age, and they are facing challenges maintaining the line due to its location on the side of the southern ridge of Fort Payne.  The Fort Payne District 46-kilovolt Substation represents an increasing reliability risk due to its advanced age and the lack of in-house options to address issues on the 46-kilovolt transmission line which supplies the station.

TVA and FPIA propose to address these issues by building a new 161-kilovolt delivery point which would include the construction of FPIA’s new Star Gap 161-kilovolt Substation and about 3.5 miles of new TVA 161-kilovolt transmission line originating at TVA’s Fort Payne 161-kilovolt Substation.  This effort will also include retiring FPIA’s existing Fort Payne District 46-kilovolt Substation as well as their existing pair of 4.1-mile, 46-kilovolt transmission lines.  The Alternative 46-kilovolt line will be deconstructed before TVA’s proposed 161-kilovolt transmission line is built.  FPIA’s existing Fort Payne District 46-kilovolt Substation and Primary 46-kilovolt feed line will remain in service during construction of the proposed substation and transmission line and will be deconstructed following their completion.

FPIA will build the Star Gap Substation at the corner of 8th Street NE and Wallace Avenue NE in Fort Payne.  TVA will build about 3.5 miles of single-circuit transmission line using primarily single-pole, steel structures with the potential for H-frame structures as dictated by the terrain.  TVA’s line would begin at the existing Fort Payne 161-kilovolt Substation and extend southwest to the new Star Gap Substation. 

TVA’s proposed line will utilize a combination of existing and new rights of way.  TVA will acquire additional easement as needed for the new line. 

TVA will hold an information day on May 1, 2025, to provide information and answer questions about the proposed transmission project.  For those unable to attend the information day on May 1, TVA is providing a virtual information session from May 1 through May 30, 2025, online at tvavirtual.com/stargap.

The project is expected to be in service in fall 2028.  Construction is scheduled to begin in spring-summer 2028.  (Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Single Pole Circuit Double circuit transmission line

Public Involvement

TVA is committed to working with area stakeholders to address concerns during various stages of the project.  TVA will hold an information day and virtual information session to discuss the proposed transmission project. Details are as follows:

Thursday, May 1, 2025, 3:00 - 7:00 p.m., local time
The Building,
301 Gault Avenue
North Fort Payne, Alabama 35967

TVA representatives will be available at the information day to provide information and answer questions. Large maps showing the alternative locations for consideration will be available.

Any questions received, including names and addresses, will become part of the administrative record.

If you have special needs, please contact Tanya Adams at least five days prior to the information day toll-free at (800) 362-4355.

If you cannot attend the information day but have questions, contact Kevin Casler (see contact information below).

SUBMIT QUESTIONS ABOUT THE PROJECT

Map

The map shows the area of the proposed transmission improvements. The map is also available below as a PDF file.

If you have questions or need help understanding the map, please contact TVA (see below).

Star Gap, Alabama Open House Map

Project Schedule

(Dates are subject to change. Unexpected issues may arise, resulting in the need to adjust the schedule.)

Information DayMay 1, 2025
Virtual Information SessionMay 1 through May 30, 2025
Surveys of the right of way are scheduled to beginSummer–Fall 2025
Easement purchases are scheduled to beginFall 2026–Winter 2026-2027
Construction is scheduled to begin Spring–Summer 2028
Project in service Fall 2028

Environmental Reviews

The appropriate National Environmental Policy Act review will be conducted to ensure that the environmental impacts are minimized. TVA attempts to minimize any land requirements, private property impacts, and environmental impacts associated with this project.

Efforts are made during the siting process to avoid or minimize impacts to floodplains and wetlands in accordance with Executive Orders 11988 and 11990. Floodplains and wetlands are shown on the referenced map. The map illustrates how the route avoids or impacts floodplains and wetlands. Because of project and topographic constraints and because of minimizing impacts to other social, environmental, and engineering resources, no practicable alternative may be available that would allow complete avoidance of impacts to floodplains and wetlands which may require mitigation for minimizing impacts. Also, best management practices would be utilized throughout the project to minimize adverse floodplain and wetland impacts. In compliance with Section 404 of the Clean Water Act, TVA will be coordinating wetland findings with U.S. Army Corps of Engineers.

Contact

More information on this project can be obtained from:

Kevin Casler, P.E.
[email protected]
800-362-4355
1101 Market Street, MR 4G
Chattanooga, TN 37402-2801