  • TVA is hosting a public open house in West Point on November 14 to get public input on a proposed transmission project.
  • The proposed project is 18-miles of transmission line from West Point to Artesia. 

WEST POINT, Miss.  ­— The Tennessee Valley Authority is asking for public input on proposed transmission system improvements to continue to serve growing electrical load and increase power reliability in the Clay, Lowndes, and Oktibbeha County areas of Mississippi.

TVA proposes to build about 18 miles of single-circuit transmission line to connect the Clay 500-kV Substation in West Point and the Artesia 161-kV Substation in Columbus. The new line would be built using primarily single-pole structures centered on new 100-foot-wide right of way. 

TVA is hosting an open house in West Point, Miss. on November 14.

  • What: Proposed Transmission Project Open House
  • When: Thursday, November 14, 2024, 12:00 p.m. - 7:00 p.m. CT
  • Where: The Civic, 130 6th Street, West Point, Mississippi
  • Other: TVA staff will answer questions, discuss concerns, and receive comments. More  information, including maps and the project schedule, is available on TVA.com. For those unable to attend the open house, TVA is also providing a virtual open house through December 16, 2024.

The public may also submit comments by contacting TVA’s Bethany Butler toll-free at 800-362-4355, by email at [email protected] or by mail to:

Bethany Butler
Tennessee Valley Authority
1101 Market Street, MR 4G
Chattanooga, TN, 37402-2801

The deadline for comments is December 16, 2024.

TVA reports the region is growing three times faster than the national average and the University of Tennessee’s Baker School projects our region’s population to grow 22% by 2050. To support this growth on a local level, TVA is investing $2.8 billion to strengthen the power grid across its service area through 2027. With nearly 60% of TVA’s energy already carbon-free, these power grid improvements will help ensure the region’s energy security as the agency provides reliable, affordable, resilient, and clean energy. To help homeowners and businesses save money on their energy bills, learn more about how TVA is offering rebates and incentives at energyright.com/rebates.

About TVA

The Tennessee Valley Authority is the nation’s largest public power supplier, delivering energy to 10 million people across seven southeastern states. TVA was established 90 years ago to serve this region and the nation by developing innovative solutions to solve complex challenges. TVA’s unique mission focuses on energy, environmental stewardship, and economic development. With one of the largest, most diverse, and cleanest energy systems – including nuclear, hydro, solar, gas, and advanced technologies – TVA is a leader in our nation’s drive toward a clean energy future.

TVA is a corporate agency of the United States, receiving no taxpayer funding, deriving virtually all of its revenues from sales of electricity. In addition to operating and investing its revenues in its electric system, TVA provides flood control, navigation, and land management for the Tennessee River system, and assists local power companies and state and local governments with economic development and job creation.

Contact

Julia Wise
Memphis
[email protected]