The following includes a list of Boone Dam current and historical questions and answers. The questions come from members of the public via the Boone e-mail program through our monthly newsletter, our Twitter feed and other directly submitted questions.
We have at least four more months of construction expected with cutoff wall completion expected in early 2021 followed by verification and reservoir testing during 2021.
Tables will be provided at the public meeting on October 15.
TVA will provide notice of the public meeting, which will likely be a virtual meeting, through its twitter feed, newsletter and notice to area media.
TVA will begin raising the lake at a rate of two feet per week from mid-October to mid-November. It will hold at a range of 1358-1362 feet from mid-November 2020 until mid-March 2021.
From mid-March 2021, TVA anticipates raising the lake at the rate of two feet per week with occasional elevation holds for varying periods of time. Depending on timing and rainfall the reservoir may be near or at summer pool during 2021 and will be returned to the normal operating guide curve in 2022. We will provide more details at the October 15 public meeting.
No, however, TVA is working with TWRA on messaging for boater safety. Recreational lake users will notice TWRA safety signage at many of the boat ramps and marinas. All lake users should be particularly vigilant in looking for hazards as lake levels are changing.
After mid-March 2021 we plan to continue to raise the lake at two feet per week with periodic holds, expecting to reach summer pool in 2021, followed by a return to winter pool of 1364 in fall of 2021.
We are concluding the supplemental vegetation management phase of our good neighbor outreach now as we complete mulching and herbicide applications at current lake levels. We will then move into the lake restoration phase in which the water raise will allow access by our barges to more challenging cove areas via water.
TVA is attempting to balance concerns for boater safety with anglers’ concerns for fish habitat. We are working with the TWRA, Boone Lake Association, the Boone Dam Repair Coalition and local fishing groups to accomplish these goals. We anticipate vegetative structure will remain below elevation 1360 in areas around the lake to benefit the fish recovery and sport fishing opportunities.
Recreational lake users will notice TWRA safety signage at many of the boat ramps and marinas. All lake users should be particularly vigilant in looking for hazards as lake levels are changing.
TVA requests that residents complete removal of low-lying items including docks and other debris by October 31, 2020. TVA will begin marking docks with requests to secure, repair, remove or relocate in accordance with the 26a permits.
October 11, 2019 Update
In accordance with the Environmental Assessment, “Mowing vegetation on the exposed reservoir bottom would not be intended to eliminate the vegetation. When the reservoir is returned to normal operations, vegetation that established in areas of the reservoir bottom during the drawdown will be inundated with water. The amount of newly established vegetation is expected to be considerable. Upon return to normal reservoir levels, public safety issues would return to pre-drawdown levels, after a period of adjustment.” TVA plans to re-asses vegetation mulched in FY19 and evaluate new areas to be mulched in FY20. Supplemental Vegetation management will continue through the 2020-2021 season prior to reservoir fluctuations.
At the September 2018 meeting TVA estimated there was approximately 1400 acres exposed between summer pool & Interim lake levels; of which TVA identified approximately 700 acres to target in general. After field review, the areas identified totaled 512 acres with reductions due to machine accessibility and or culturally sensitive sites. Results of the Fiscal Year 19 efforts are below.
No, TVA continues to meet the Environmental Assessment with regards to the Supplemental Vegetation Management Plan.
TVA has completed 25 elements with approximately 30 additional elements in some stage of progress. Secant progress was/is set to vary as the project moved from the “technique” portion of the wall to production and based on location with the embankment itself.
The layout of the cutoff wall has not changed. However, geometry and as-built quantities vary by geologic condition as installed in the field.
See above for #4 and #5. Schedules are updated daily based on progress. As such, secant totals vary for each month. Schedules are updated and published to this web site monthly.
The cutoff wall is on schedule to complete in spring of 2021. Completion of secants each month varies based on geometry within the dam and geology at discreet locations along the profile as well as potential weather impacts.
Yes. A high level construction schedule update is and has been provided to the public each month on the Boone Dam Repair website with details provided at public and media updates.
The equipment in use varies based on the daily task, currently there are more than half a dozen pieces in use as can be seen in media photos and TVA’s weekly community relations updates (see @BooneRepair twitter, monthly e-newsletter and the website).
Incentives are included in the contract, details are bound by confidentiality agreements.
Penalties are included in the contract, details are bound by confidentiality agreements.
The wall is a minimum of 24 inches thick, approximately 840 feet long, and varies in depth from approximately 100 to 180 feet below the working surface.
TVA will complete the wall by May 2021 and is on schedule to return the reservoir to the normal operating guide curve by July 2022.
The wall will be built using overlapping, reinforced construction elements.
Mobilization will begin in Fall 2018. A tremendous amount of pre-work is involved in preparing the site ahead of time for construction. Some of that can be seen already in terms of the laydown yard construction and new employee parking lot at Boone Dam. Construction will begin in May 2019.
So far, we have spent more than $120 million and we remain on budget.
The $300M was a benchmark from various U.S. Army Corps of Engineers jobs to build a cut off wall. The complete $457M project number announced in 2017 includes a significant amount of additional work that makes Boone very safe and robust, such as the buttresses up and down stream and the high and low mobility grouting programs.
This increase will help ensure the commitment to return Boone Lake to the community while maintaining the safety of the downstream public. Budget changes are normal as the design & construction progresses and will be refined throughout the project.
We have completed the grouting necessary for stability of the earthen embankment during construction of the cutoff wall. Quality of the repair is one of our Top Priorities in this project. To ensure the repair is of the highest quality and robust as it can be, we are doing some additional grouting this fall. However, this does not indicate any additional problems and it is not tied to the timing of cutoff wall construction and the subsequent schedule for the refill plan.
TVA signed non-disclosure agreements with each of the companies involved. However, the cost is included in the $457 million total project budget, and we remain on track to meet that budget.
We received multiple competitive proposals. Again, TVA signed non-disclosure agreements with each of the companies involved.
The notifications for selection and non-selection were made July 31, 2018.
We will have a total work force of approximately 200 people when we are running at full capacity and certainly a portion of those are local.
We expect there will be phases of the wall construction that will operate 24 hours per day.
We’ve completed some work on reinforcing the upstream and downstream sides of the earthen embankment. After completing the majority of the early grouting work, this current phase of the project is in preparation for starting construction of the composite seepage barrier later this year. We’ve named Treviicos-Nicholson Joint Venture to construct the underground cutoff wall. We are still targeting completion of the project in 2022 at a cost of up to $457 million.
TVA has completed seepage barrier projects in the past but has not built a composite seepage barrier, including a cut-off wall, of this magnitude.
Numerous projects and Treviicos was a key partner in the Wolf Creek Dam Repair and Nicholson has worked on multiple TVA dams including Boone.
Yes.
No.
May 2019.
May 2019.
Yes. TVA will provide the major milestones in the remaining work and update the public monthly via our public communication channels including this web site.
The berms and procurement of the cutoff wall contractor were completed ahead of the initial project schedule. TVA has never stated that the wall will take only 18 months to complete. We will complete the wall by May 2021, and we have consistently stated that we are on schedule to return the reservoir to the normal operating guide curve by July 2022.
Approximately 300 sections or elements, generally 100 to 180 feet deep, approximately 835 feet in total length.
Estimates vary significantly by location, geometry of the element and geology along the profile.
Yes.
The contractor is expected to work 5 days per week/24 hours per day with a day shift on Saturday once the production of the wall starts.
The current physical wall installation schedule is May 2019 to May 2021. This timeframe does not include any required infrastructure construction or the closeout of documentation. It also does not consider the observation and testing period necessary after the completion of wall construction. As previously stated, the project is expected to be complete and the lake returned to its normal operation by July 2022.
Due to confidentiality terms and agreements, the specific details of the contract, including incentives, will not be discussed publically.
Yes. We are on track, on scope and on schedule. Since July 2015, construction of the composite seepage barrier has been moving forward on schedule for completion in calendar year 2022.
We are on schedule for completion of construction in calendar year 2022. This is within the estimated completion timeframe we first announced in July 2015.
Work to date includes:
The berms provide additional stability for the earthen embankment and an improved working surface for wall construction. Construction on the upstream and downstream berms was pulled ahead to provide additional strength to the dam as construction resumes.
Since the start of the project, certain aspects of the repair work (i.e. workforce on site, grouting techniques, order and sequence of repair activities, etc.) were designed with the flexibility to be refined or modified as needed as new data are gathered.
The temporary construction stoppage, resequencing of planned activities, and other such refinements are expected in these types of major construction projects and were anticipated in the estimated five-to-seven year timing of the Boone Project plan.
The project remains on schedule and we will continue to monitor data to make any additional adjustments necessary to ensure the safety the public and quality of the repair.
Boone Dam is structurally sound. Safety of our employees and the general public is our top priority. We continuously monitor the dam and surrounding structures so that we’ll know if there are changes in its condition. The current project began after investigations indicated that, under normal operating levels, erosion was occurring deep underneath the earthen dam and could worsen if not repaired, threatening the stability of the earthen portions of the dam.
Actually, it did. Plant employees trained to identify dam safety issues—part of the overall dam safety program—were the first to identify this issue.
TVA has a robust dam safety program with comprehensive inspections and monitoring. We’re also performing “health checks” on all 49 dams to thoroughly analyze their conditions.
TVA is fully committed to the safety of the public we serve. We have numerous monitoring systems, as well as routine health checks and inspections, to maintain awareness of the condition of our facilities. Although dams are complicated structures that require periodic maintenance, the situations we have encountered at Pickwick and Boone are separate and distinct issues and we are taking the necessary steps to correct them.
Yes. At other dams with seepage in the past, the source has been identified, and the dams have been successfully repaired. Those include TVA’s Tims Ford, Bear Creek, and Little Bear Creek Dams. In addition, the U.S. Army Corps of Engineers’ Wolf Creek Dam had similar issues which were repaired in 2013.
Overall, our dams have held up exceptionally well over decades—and sometimes, centuries—of use. Like any “machine,” dams do require preventative maintenance. Our dam safety program is designed to help us identify any potential issues very early and correct them before they could ever cause a safety issue. TVA has spent more than $390 million on river dam improvements since 2010.
While no one can guarantee zero future risk, this fix will minimize risk as much as possible. We recognize our responsibility to maintain and operate all of our facilities in a way that protects the health and safety of the public. In addition to regular maintenance, we have monitoring and assessment programs in place to quickly identify any potential issues in their earliest stages, which allows us to correct them as quickly, effectively and safely as we can.
In the highly unlikely event that a TVA dam were to fail, there are Emergency Action Plans (EAPs) in place to quickly notify response personnel and alert the public. TVA works with counties, states, National Weather Service, and a host of other partners to prepare for such an event. Boone Dam is monitored 24/7 by highly trained engineers. This provides TVA the ability to react to changing conditions day and night. If any of the monitoring signals an event, TVA will immediately notify the affected counties to begin evacuations, and the National Weather Service to broadcast a Dam Failure Flood Warning to the public.
If the erosion of the embankment were to continue and the dam were to fail, the impact downstream would be significant. Homes, businesses and recreational areas would be flooded and thousands of lives would be placed in danger. It is for these reasons that we must maintain lower reservoir levels while we safely correct the seepage problem.
The issues faced at Pickwick and Boone are different, and TVA is fully committed to the safety of the public we serve. We have numerous monitoring systems, as well as routine health checks and inspections, to maintain awareness of the condition of our facilities. Although dams are complicated structures that require periodic maintenance, the situations we have encountered at Pickwick and Boone are separate and distinct issues and we are taking the necessary steps to correct them.
The natural karst geology of the area has allowed water to gradually erode the foundation soils over time, creating additional pathways for groundwater in and under the embankment. If left uncorrected, this erosion could eventually undermine the foundation of the embankment and lead to the failure of the dam.
In dealing with the complexities of karst geology, Boone Dam was constructed using the best construction methods available in the early 1950s. Over time, foundation soils under the embankment have slowly eroded causing water pathways to develop. The proposed repair will prevent further erosion.
While no one can guarantee zero future risk, this fix will minimize risk as much as possible. We recognize our responsibility to maintain and operate all of our facilities in a way that protects the health and safety of the public. In addition to regular maintenance, we have monitoring and assessment programs in place to quickly identify any potential issues in their earliest stages, which allows us to correct them as quickly, effectively and safely as we can.
The sinkhole was repaired with low mobility grouting. The cut-off wall mitigates the seepage from the reservoir.
Yes, there is continuing evidence of seepage which is why the cutoff wall must be completed as part of the composite seepage barrier. No further repairs to the embankment are currently anticipated beyond the construction of the cutoff wall and crest restoration.
During the exploratory drilling and grouting efforts, we did confirm the presence of karst features (enlarged bedding planes, open bedding planes, etc.)
No other TVA dams were identified to have problems similar to Boone because geology varies locally/regionally. In karst terrains, that geology is even more variable.
The Environmental Assessment assesses potential environmental impacts and stated that TVA’s objective in managing vegetation is to ensure that there are no safety or navigation hazards once waters are returned to normal levels. The EA states that vegetation growth would be managed on an annual or periodic basis. TVA intends to limit the frequency of mechanical equipment in the lakebed to reduce mechanical erosion impacts.
TVA is continuously seeking options to mitigate or lessen local project impacts, and one of the areas currently being re-assessed is the need to use Earl Light for spoils disposal. We will notify the public of any change in plans for the potential use of this area for spoils disposal.
The lake will have a period of fluctuation, potentially up to summer pool following completion of the barrier, planned for 2021. Once the data is reviewed and submitted, the lake will be returned to the normal operating guide curve in 2022. When would the refill process start, and has that been integrated with the new contractors cutoff wall repair completion schedule? Refill is part of the overall project plan and will begin after completion and verification of the final element.
The observation period will begin after construction of the composite seepage barrier, which is scheduled for completion by May 2021. We will notify the public before beginning any intentional changes to the lake level.
There is no set time period. The duration of the refill period and the time needed to return to normal lake levels and normal operating guide will be based on many factors, including results of our ongoing observations, the amount of rainfall that occurs during the refill period, the time of year the wall is completed and the normal operating guide for that time of year. As always, safety will remain our top priority during the refill.
For safety purposes the lake levels will remain at lower levels during construction. However, project engineers will evaluate the potential of raising the water, if possible, through the course of the project. Interim fluctuations of the lake level as much as 5 to 10 feet above the current pool level may occur to facilitate future evaluations of the dam remediation. These fluctuations will be communicated to stakeholders a minimum of 60 days prior to any changes in lake levels.
In an average year, TVA prevents about $250 million in flood damage in the TVA region and along the Ohio and Mississippi rivers through the operation of its dams. Overall, TVA has averted more than $7 billion in flood damages.
Above average rainfall this past winter and early spring helped hasten annual spring fill and kept lake levels at or above normal during summer 2018. Both tributary and main Tennessee River lakes have been in good shape in reaching summer lake level targets.
Yes.
No, the information is safety sensitive and pre-decisional.
Yes, future interim fluctuations are being considered with potential elevations to help refine and potentially accelerate the refill plan. Safety of the downstream public remains the top priority of the project.
The reservoir currently applies a pressure which is approximately 40 psi greater than that imposed within the river downstream of the dam. This pressure differential increases slightly more than 4 psi for each 10-ft incremental increase in the reservoir elevation.
No. TVA’s Operating Guide is based on flood prevention. Intentionally exceeding the Operation Guide standards at any reservoir would significantly increase flooding risks on both that reservoir, as well as those downstream.
TVA has provided in-lieu fees to the area but does not place constraints on how those funds are spent by the entities that received them. TVA and project employees volunteer actively in the BLA lake cleanup days.
No.
The drawdown has not reduced the reliability or ability to meet the power needs.
There have not been rate increases due to the project. The project is within TVA’s normal operating budget, which has actually been reduced by $800 million/year since the project began.
The completion date and budget are based on the tasks necessary to build the cutoff wall and ensure safety of the downstream public, safety of the workers and quality of the repair. While we always attempt to complete our work efficiently, the complete date and budget cannot be arbitrarily changed without impacts to one of those commitments and result in an incomplete project.
For safety purposes the lake levels will remain at lower levels during construction. However, project engineers will evaluate the potential of raising the water for assessment purposes through the course of the project.
Even after construction is complete, there will still be testing, monitoring, inspection and other very important work to be done. We will be raising the lake level slowly and looking at it very closely to ensure the seepage and erosion is stopped, the repair is sound, and the embankment is stable after the repair is done. The reservoir fill rate at that time will depend on the data we have gathered during the project, readings from our instruments, and other factors, but we will be proceeding with an abundance of caution. Safety will always be our top priority.
TVA is working with local residents, businesses, elected officials, TWRA, and others to address vegetation growth during the Boone Dam Project in a safe, sustainable, and environmentally responsible way.
TVA’s vegetation management plan will emphasize safety, stewardship and a balanced approach, and focus on communicating with homeowners, identifying high-use areas for supplemental vegetation management, utilizing specialized equipment and machinery and creating and implementing a schedule for vegetation work over the next two to three years.
While the vegetation is beneficial to the natural health of the lake, TVA understands homeowners’ concerns and will work with them during this project to address those concerns.
TVA will work with the public to identify and manage selected tracts and acreage in the drawdown area, especially high-use areas where vegetation may pose safety or navigational threats. TVA also will make maps and other informational materials available to show areas where work will be done.
In areas near homes, marinas or businesses, TVA will notify and communicate with those homeowners and business owners in advance of vegetation management work. Only vegetation below normal summer pool (1382 feet) will be cut, and our flowage easement extends to the 1390-foot contour.
Trees and shrubs also will be shredded and mulched. Large trees will be pruned to a maximum elevation of about five feet below winter pool.
TVA plans to invest more than $2 million in vegetation maintenance at the Boone Dam drawdown area.
Environmental Stewardship is a core mission of TVA’s, along with energy and economic development. The vegetation improves water quality, provides aquatic habitat, prevents erosion, and helps create a sustainable shoreline. TWRA requested formally in writing that TVA not cut vegetation unless absolutely necessary for operations or navigation.
TVA also has conducted aerial, boat and land surveys and GIS mapping, formed cross-functional teams to survey, assess and reduce vegetation growth, and also plans to hire a vegetation maintenance liaison to communicate specifically about vegetation management.
TWRA and TVA partnered to plant 400 acres of vegetation on the lake shore, including 12 acres within the Lake Harbor view shed.
TVA has a vegetation work group: we are evaluating next steps.
View the online vegetation management brochure for homeowners.
TVA is looking to provide some shoreline vegetation management assistance for Boone residents on a voluntary basis.
To prevent erosion on the exposed shoreline at Boone, property owners can sow annual rye grass, which tends to germinate quickly, even during cooler fall temperatures and can provide good ground cover through the winter months. You also can choose native plants this spring to beautify your property and hold soil in place. Switchgrass, little bluestem, Indiangrass, cardinal flower, coneflower, sunflower and milkweed are all good low maintenance options and will not create any navigational hazards when water levels return to normal on Boone. More information can be found at the Boone Website.
The majority of Boone Lake properties (above and below water) are privately owned, and TVA has obtained flowage rights. Unless TVA has reserved rights for the public, crossing private property is generally a civil matter and may involve private trespass issues. Local law enforcement may need to be involved. Property owners should be reminded that, if they decide to use certain measures to prevent trespassing (i.e., signage, fencing, etc.), those measures could become subject to TVA’s Section 26a regulations, which require TVA approval be obtained before any construction or other alterations are carried out that affect navigation, flood control or public lands along the shoreline of TVA lakes or in the Tennessee River or its tributaries.
Yes, the Supplemental Vegetation Management Plan has been developed with both planned locations and draft schedules. Additional details will be posted on the Boone Project website soon.
TVA continues to review its supplemental vegetation plan with our longstanding partners at the lake including TWRA, BLA and ETSU (cultural resources). In addition, TVA continues to accept and review requests from the public for areas to assist with vegetation and areas that the public does not want vegetation management by TVA.
No, clear cutting is not beneficial for the environment and TVA is not supplementing vegetation management for recreational boating but TVA intends to maintain navigation access while balancing erosion control, wildlife habitat, and long-term fish health for the lake.
None. Efforts, such as maintenance of supplemental vegetation management, come from a different funding source than the repair project.
The Environmental Assessment assesses potential environmental impacts and was never intended to be a “work plan.” The frequency of the effort was assumed to be worst case scenario to fully capture potential impacts. Limiting the use of mechanical equipment in the lakebed also reduces erosion impacts, which can cause property damage both before and after the lake returns to normal operation.
Cutting and mulching will be the primary vegetation management methods and also will help to prevent soil erosion.
The situation at Boone is more complicated and complex than we originally thought. To ensure the correct long-term fix, our experts needed time to fully investigate the situation, analyze data and consult with industry experts to determine the right path
forward.
The project will be completed within the initially projected 5 to 7 year timeframe that was outlined in our July 30, 2015 public meeting.
TVA came to its estimate that the project would take 5 to 7 years based on several considerations, including the complicated nature of the proposed remediation action and the experiences of other agencies in conducting similar projects. TVA must also account for the safety of its workers when determining how quickly to conduct very complicated construction activities.
As described in Chapter 2 of the EA, the remediation project requires extensive grouting and the construction of a concrete wall deep into the earthen embankment of the dam. Grouting will require drilling hundreds of separate holes deep into the underlying bedrock. Because the working space atop the earthen embankment is limited, TVA is limited in how many drilling and grouting rigs can work simultaneously. In addition, the construction of a deep, linear wall into the earthen embankment is very complicated; great care must be taken to ensure that the embankment remains stable during construction. In estimating the timeline, TVA also went through benchmarking of similar seepage remediation projects (including some lasting more than 10 years) that were conducted by other agencies or companies and determined that the proposed project timeline is realistic.
Please also note that TVA’s initial 5- to 7-year estimate included the planning and design period of the project. This period involved extensive investigation to characterize the nature and extent of the seepage issues, consultation and design
evaluations with experts in dam safety and engineering, completing numerous environmental and permitting requirements, and mobilization of the resources for construction. TVA completed this phase of the project within 18 months of its discovery
of the seepage at Boone Dam. For similar projects, planning and design has required at least 3 years.
For safety purposes the lake levels will remain at lower levels. However, project engineers will evaluate the potential of raising the water, if possible, through the course of the project for assessment purposes.
Boone Reservoir currently operates between 1,350 and 1,355 feet above sea level, and about 10 feet below normal winter pool, though reservoir levels could vary if conditions change.
As a prudent and conservative measure to maximize the safety of those living downstream, TVA has lowered the level of the Boone Reservoir to about 10 feet below normal winter pool elevations, which both reduces the hydrostatic pressure on the components of the dam and reduces the volume of water that would be released in the unlikely event of a dam failure.
If the erosion of the embankment were to continue and the dam were to fail, the impact downstream would be significant. Homes, businesses and recreational areas would be flooded and thousands of lives would be placed in danger. It is for these reasons that we must maintain lower reservoir levels while we safely correct the seepage problem.
TVA estimates the project costs up to $457 million.
TVA effectively manages its normal operating budget to provide for such unexpected projects, so there should be no significant impact to ratepayers.
Yes. After the initial two years of work, TVA revised the project cost range estimate from the $200-$300 million range estimated in 2015 to a current range estimate of about up to $457 million.
TVA has added detail to the project baseline for activities and re-forecasted estimates to include contingency funds for those activities. These contingencies may or may not occur, so these funds may or may not be used. As a result, the overall funding limit requested by the project has increased.
This increase will help ensure the commitment to return Boone Lake to the community while maintaining the safety of the downstream public. This is normal as the design & construction progresses and will be refined throughout the project.
Other factors impacting the revised cost range estimate include refinements to the project work plan and modifications to maximize quality and safety. Also, the work completed over the past three years has given project engineers better data for estimating
costs. As work progresses, those estimates will continue to be refined to narrow the final project completion cost range.
We do not have any plans to purchase property. We are committed to fixing the earthen embankment as quickly and safely as possible.
The houses purchased at Kingston were directly damaged by the ash spill or were impacted by the 24/7 heavy equipment activities associated with the remediation. While we understand that homeowners’ access to Boone Lake will be impacted during the project, there is no physical damage to homes as a result.
While removal of boats is not something TVA is considering, we will keep the Boone residents and users informed should we significantly fluctuate lake levels.
We recognize that many are impacted by the lower water levels, but marina owners in particular gain their primary income from the lake. We provided other ways to help the community such as new and improved boat ramps for deep water access and a new swim beach.
We improved or created three access areas: expanding the current boat ramp at Pickens Bridge, installing a new ramp at Devault Bridge with TWRA and created a new swim beach and boat ramp just northeast of the dam on Minga Road.
Yes. We anticipate some local sub-contractors and suppliers will be used. In addition, any contract personnel are likely to take advantage of local hotels, restaurants and stores, creating additional economic activity in the community.
The University of Tennessee recently conducted a study of economic impacts, so we recommend you contact them for additional information visit http://aimag.ag.utk.edu/.
The TVA Independent Dam Safety Review Board, consisting of experts in dam safety and operation from across the country, actively monitors the work on Boone Dam, along with TVA Dam Safety Governance & Oversight and the TVA Office of the Inspector General (OIG).
The EPA is not involved. However, TVA follows the National Environmental Protection Act (NEPA) process which dictates environmental compliance for federal agencies.
The U.S. Army Corps of Engineers has been serving in an advisory role along with other dam owners in the U.S.
We work with TDEC (Tennessee Department of Environment and Conservation) to monitor water quality.
TVA fisheries biologists are working with TWRA (Tennessee Wildlife Resources Agency) to monitor the fish habitat at Boone. Currently we don’t anticipate any impacts.
No, the work and status at Boone do not impact the safe operation of the TVA nuclear fleet. All three of TVA’s nuclear sites have been evaluated for the flood levels downstream of Boone, and safe operation of the plants has been confirmed. An analysis has been performed that shows any potential flood water from Boone Dam is adequately controlled by Cherokee and other downstream dams.
We are committed to keeping the community informed. For monthly updates, check tva.com/boonedrawdown and follow the project on Twitter @BooneRepair. The project team is also available for speaking engagements. As the project progresses, we will also continue to hold regular meetings to update the community on the status of our work.