.skip-nav {position:absolute;left:-10000px;top:auto;width:1px;height:1px;overflow:hidden;} Skip to main content <
Skip to main content
Chatuge Dam

Chatuge Dam Safety Modifications

TVA is currently seeking public input on proposed changes to Chatuge Dam to address potential risks to the dam’s spillway. Public comments are being accepted through May 28, 2025, and can be emailed to [email protected].

These options are:

  1. Alternative A: No Action – TVA would not perform any modification of the Chatuge Dam spillway, valves or embankment and would continue to maintain these components in their current condition. TVA would continue to monitor and inspect the spillway, repairing joints and sealing cracks in the spillway slab and walls as they are identified; however, the risk of spillway damage and failure would continue to exceed TVA’s risk tolerance.
  2. Alternative B: Remediation in Place – Repairs would take place on the existing spillway while the dam remains in operation. The dam powerhouse would also have updated valves and piping installed, which is part of each of the alternatives included in the study. This option requires drawing down the reservoir during construction, which would take up to 8 years to complete.
  3. Alternative C: Remediation with Concrete Liner – The existing spillway would be covered with a new concrete liner. The reservoir would need to be drawn down during construction, which would take up to 6 years to complete.
  4. Alternative D: New, Larger Spillway – A new spillway would be built. When complete, the existing spillway would be abandoned. This option requires excavation of rock and material that may be used for improvements to the dam embankment. Total construction time would be up to 6 years. The reservoir would need to be drawn down for a period of up to 4 years.
  5. Alternative E: New Spillway and Repairs to Existing Spillway – A new spillway would be built, with similar capacity to the existing spillway. Once complete, the existing spillway would be repaired for use as a second spillway during rare, extreme weather events. Excavated material may be used for improvements to the dam embankment. Construction time is estimated at 7 years, with the reservoir needing to be drawn down for up to 5 years.

Download renderings for the alternatives.


All options except option A include additional improvements to the powerhouse, valves and piping. Spillway work could also provide an opportunity to improve the site with rock buttresses along the face of the dam and around the reservoir rim, improved drainage at the base of the dam and downstream channel improvements. These optional projects would improve operations at Chatuge.

Public Meetings

May 13: In-person – Open House from 5:00 to 7:00 p.m. ET at Towns County Recreation Center, 150 Foster Park Rd., Young Harris, GA 30582
Format: Informational booths and materials. Access to subject matter experts. No formal presentation.

May 15: Virtual Meeting from 5:30 to 6:30 p.m. ET
Format: Dam Safety and NEPA presenters with a Q&A session
Register here.

Meeting Recordings

May 6, 2025 

Learn more as TVA dam safety project manager Chris Saucier answers questions about Chatuge Dam.

In the News

Local and regional media coverage of the Chatuge Dam and spillway study and community engagement.

Adam May and Chris Saucier interview (mp3) – April 25, 2025
WKRK, Murphy, North Carolina

Georgia News Network (mp3) – April 22, 2025

Chris Saucier interview (mp3) – April 21, 2025
WJUL, Hiawassee, Georgia

Chris Saucier interview (mp3) – April 7, 2025
WJUL, Hiawassee, Georgia

Chris Saucier radio interview (mp3) – Jan.18, 2024
WJUL, Hiawassee, Georgia

NE Ga. dam coming under scrutiny – April 22, 2025
Georgia News Network

Rep. Clyde visits Chatuge Dam to advocate for a sensible approach to address spillway vulnerabilities – April 21, 2025
Press Release, Gainesville, Georgia

Chatuge Dam safety modification study underway – April 3, 2025
Clay County Progress, Hayesville, North Carolina

Spillway fix to bring record-low lake levels – April 2, 2025
Towns County Herald, Hiawassee, Georgia

Multi-year safety study underway at Chatuge Dam – Dec. 28, 2023
Clay County Progress, Hayesville, North Carolina

Project Background

TVA carefully inspects its dams according to best practices in dam safety. Our dams were built to stand the test of time. Maintenance, repairs and modifications ensure continued safe operations.

New standards led to concerns about Chatuge’s spillway. The spillway releases water from the reservoir. The concrete slabs, and the drainage system beneath, have deteriorated over time. Using the spillway during an extreme weather event for an extended period could damage the spillway and, potentially, the dam.

TVA errs on the side of caution. Chatuge Dam and reservoir are critical to the safety and well-being of communities nearby and downstream. We’re focused on reducing the potential risk and ensuring the dam’s long-term safe operations.

Chatuge Dam Facts

  • Chatuge Dam and spillway are safe for operation.
  • There is a risk of water flowing over the spillway for an extended period, during a rare and extreme weather event, could damage the spillway.
  • TVA continues to monitor Chatuge Dam and perform repairs to the spillway.
  • A drawdown of the lake would bring the water level to 1908 feet, approximately 10 feet below winter pool level.
  • TVA does not have a preferred alternative at this time.
  • The Draft Environmental Impact Statement (EIS) evaluating the alternatives is expected to be completed in late 2025/early 2026. The environmental impact study for the project will continue into 2027 with a decision anticipated in early 2027. Construction could begin in late 2027 or early 2028.
  • Construction of Chatuge Dam began July 17, 1941 and was completed February 12, 1942.
  • Chatuge Reservoir covers an area of 7,000 acres.
  • Recreational facilities that could be impacted by a potential project identified at this time include:
    • 10 campgrounds
    • 9 marinas
    • 17 boat ramps (including marinas)
    • 6 paved trails
    • 6 fishing piers

Frequently Asked Questions

If a large volume of water flows quickly over the spillway, that water could lift the concrete slabs. Once a slab is lifted, the ground is exposed to the force of the water, which could erode the spillway all the way back until it breaches the reservoir. Breaching means a failure of the dam to hold back the water.

 

After the California-based Oroville Dam failure in 2018, TVA performed extensive investigations to see if Chatuge had the same potential vulnerability to its spillway. TVA has judged the spillway at Chatuge Dam exhibits some vulnerability to this potential failure mechanism and has chosen to address the issue proactively.

Additionally, the dam safety profession has moved toward incorporating greater consideration of downstream consequences within evaluations of dam safety. TVA has been integrating this approach into its dam safety program as part of its ongoing commitment for all TVA dams to conform to modern standards for public protection. This change in industry practices is one factor in TVA's efforts to increase the safety of Chatuge Dam.

We have implemented several activities to ensure ongoing safe operations, including increased monitoring of the dam, increased interactions with local emergency management agencies, and placement of emergency response resources at or near the site.

If monitoring indicates risk of further spillway damage and/or failure, the reservoir could be drawn down until repairs or safety concerns caused by worsening conditions are remediated.

We took all options into consideration, including a new dam. Due to a variety of factors, including timelines, TVA is not considering construction of a new dam at Chatuge.

Most plans being considered already integrate cofferdams to minimize the duration of construction and maintain safe working conditions within the spillway. However, discharges from the spillway remain the most effective means of preventing the dangerous condition of overtopping of the embankment dam. For this reason, cofferdams cannot be used to block flows entirely over the existing spillway during the construction of spillway repairs.

TVA has worked diligently to assess the needed time and budget to complete each of the proposed modifications to the spillway and will strive to continually keep the public informed of all efforts related to Chatuge. TVA funding for the dam safety project at Chatuge is not reliant on funding from other federal agencies or any external third parties.

TVA operates as a public power utility, meaning it's not focused on profit, but on serving the public interest and ensuring low rates. Our rates are affected by factors like fuel costs, capital investments and the need to meet growing energy demand.

TVA is still obligated to evaluate the environmental and social impacts of the proposed action under the National Environmental Policy Act. These evaluations include a study of socioeconomic impacts, which is a standard component of the NEPA reviews. This analysis will inform TVA’s final decision.

TVA has consulted with local utilities, and we don’t anticipate any repercussions for their operations. TVA will be able to maintain minimum flows to ensure water supply and aquatic health.

TVA does not currently have maps which accurately depict this contour, as the contour is below the typical water surface elevation. TVA intends to obtain data to better define the location of this contour at various locations around the reservoir during the coming year.

While temporary disruptions may be necessary, TVA will be working closely with local and state governments to maintain access to launch ramps.

Section 26a permits give permission for structures to be built in accordance with approved plans which provide the specific location, size and configuration of the structure. Any decision on how to manage potential impacts at Chatuge will require further analysis.

Any potential impacts on Parrot Feather at Chatuge Reservoir will require further analysis. TVA will perform surveys once water levels return to normal to see if additional treatment is warranted if the invasive species starts to regrow.

The safety of the public is our top priority. Due to large equipment and potential hazards, access to the crest road will not be available during construction.

Stay Informed

Sign up to stay informed about the latest on our safety efforts at Blue Ridge Dam.

Which updates would you prefer?